Superfund Information Systems: Site Profile

Superfund Site:

DAVIS TIMBER COMPANY
HATTIESBURG, MS

Cleanup Activities

On this page:

On related pages:


Background

The 30-acre Davis Timber Company site is located in Hattiesburg, Mississippi. The site includes the area where Davis Timber Company operated a wood-preserving facility from 1972 to the late 1980s. EPA placed the site on the Superfund program’s National Priorities List (NPL) in 2000 because of contaminated groundwater, soil and sediment resulting from facility operations. EPA and the Mississippi Department of Environmental Quality (MDEQ) have investigated site conditions and taken steps to clean up the site in order to protect people and the environment from contamination. Site contamination does not currently threaten people living and working near the site. By cleaning up the site, EPA and MDEQ continue to protect people and the environment from site contamination.

Top of Page


What Is Being Done to Clean Up the Site?

EPA led the site investigation and cleanup activities in cooperation with the Mississippi Department of Environmental Quality.

Cleanup began during October 2011 following receipt of remedial action funding through the President’s Jobs Initiative Program. Construction activities finished in September 2012, and included site clearing and demolition of on-site structures and installation of the impoundment liquid extraction and treatment system. This system treated about 525,000 gallons of liquid. Activities also included relocation of about 1,046 linear feet of West Mineral Creek, construction of berm impoundment, excavation of about 2,500 cubic yards of contaminated soil from the cooling pond and areas of surface soil contamination, construction of an impoundment cap, and final grading and vegetation.

EPA has implement institutional controls, including land use restrictions and deed notices, for the capped area and the site property to limit future land uses.

The first five-year review for the site was conducted in 2016, and the remedy was found to be protective of human health and the environment.

Top of Page


EPA’s Involvement at the Site

 

 

Physical remedial action construction activities began during October 2011 following receipt of remedial action funding through the President’s Jobs Initiative Program. Remedial action construction services were procured through the existing Region 4 Emergency Response and Removal Services (ERRS) contract.  Construction activities were completed in September 2012, and included the following:

 

  • Site clearing and demolition of on-site structures
  • Installation of the Impoundment liquid extraction and treatment system
    • This system treated approximately 525,000 gallons of liquid
  • West Mineral Creek Relocation
    • Relocated approximately 1,046 linear feet of creek
  • Impoundment berm construction
  • Cooling pond and areas of surface soil contamination excavation
    • Excavated approximately 2,500 cubic yards
  • East Mineral Creek Excavation
    • Approximately 525 linear feet and 120 cubic yards of soil
  • Impoundment cap construction
  • Final Grading and vegetation

 

Green Remediation Measures

 

The remedial action construction incorporated a number of green remediation measures through reuse, repurposing, and recycling of materials and on-board design optimization measures, including:

 

  • Recycling of 325,200-lb of steel recovered during demolition of site structures;
  • Repurposing clean concrete slab material into 3,000 cubic yards of rip rap for erosion protection in the re-aligned reach of West Mineral Creek;
  • Reuse of trees and shrubs collected from site clearing and grubbing for 2,000 cubic yards of mulch;
  • Optimization of the re-seeding design to incorporate drought tolerant indigenous species and soil amendments reducing the watering requirement by 30 - 35%; and
  • Reuse of treated Impoundment water for irrigation of re-seeded areas.

 

Top of Page


Green Remediation

Construction of the site’s remedy incorporated a number of green remediation measures through reuse, repurposing and recycling of materials and onboard design optimization measures. Green remediation measures included recycling of steel recovered during demolition of site structures, repurposing clean concrete slab material into 3,000 cubic yards of riprap for erosion protection in the realigned reach of West Mineral Creek, reuse of trees and shrubs collected from site clearing and grubbing for 2,000 cubic yards of mulch, optimization of the reseeding design to incorporate drought tolerant indigenous species and soil amendments  reducing the watering requirement by 30 to 35 percent, and reuse of treated impoundment water for irrigation of reseeded areas.

Top of Page


Enforcement Information

The EPA has been unable to identify any viable potentially responsible parties for the site. The EPA is using federal funds for site cleanup activities.

Top of Page

<