Superfund Information Systems: Site Profile

Superfund Site:

BOARHEAD FARMS
BRIDGETON TOWNSHIP, PA

Cleanup Activities

On this page:

On related pages:


Background

The Boarhead Farms Superfund Site is located on a residentially zoned property at 1310 Lonely Cottage Road in Bridgeton Township, Bucks County, Pennsylvania. The current owner, Boarhead Corporation, was incorporated and purchased the property in 1969.  After purchase, Boarhead Corporation began storing and conducting activities that led to the release of hazardous substances to the environment.  In 1970, a fish kill in a nearby stream was traced to releases of wastes from the site.  Early investigations by the Bucks County Department of Health and the Pennsylvania Department of Environmental Resources (now Department of Environmental Protection) reported, among other observations, liquid wastes stored in 55-gallon drums, tanker trucks or trailers, and various containers, and liquid wastes pooled on the ground.  Disturbed soils were observed, which inspectors believed to be indicators of buried waste. 

In September 1976, approximately 34 local residents were evacuated due to the presence of sulfuric acid vapors that emanated from the site.  These observations contributed to an order in October 1976 by the Bucks County Court of Common Pleas for Boarhead Corporation to remove all wastes from the site and prohibit the transport of hazardous substances onto the site at quantities greater than those that would be appropriate for normal household use.  EPA has addressed the releases of hazardous substances through a variety of actions and continues to oversee on-going work, which includes but is not limited to on-going operation and maintenance of a groundwater extraction and treatment system on the site and point-of-entry treatment systems on residential potable wells both on and off the site.

Top of Page


What Has Been Done to Clean Up the Site?

EPA’s involvement at the site began in 1984 with the performance of preliminary assessments and site inspections and has continued to the present date.  Observations made during these assessments and inspections led to the addition of the site to the National Priorities List (NPL) in 1989.

Three removal actions were conducted in the 1990s:

  • Excavation and off-site shipment of buried drums and impacted soils containing hazardous waste (1992-1993 by EPA);
  • Off-site shipment of buried drums containing radioactive hazardous waste (1993 by a potentially responsible party (PRP) under EPA oversight); and
  • Construction of a groundwater extraction and treatment system (1995-1997 by the U.S. Corps of Engineers).

During performance of these removal actions, EPA conducted a remedial investigation and feasibility study (RI/FS) to determine the nature and extent of contamination, evaluate risk, and assess the practicality of potential remedial alternatives. The findings of the RI/FS were used to identify remedial action objectives and select a remedy, which was presented in a November 18, 1998 Record of Decision (ROD). The remedy included the following principal components:

  • Soil aeration and treatment of surface soil at two “hot spots";
  • Excavation and off-site disposal of buried drums;
  • Groundwater extraction and treatment using precipitation and air stripping;
  • Installation of additional groundwater monitoring wells to monitor effectiveness of the remedial action;
  • Maintenance of individual granular activated carbon filters installed on certain residential supply wells to prevent potential exposure to contaminated groundwater;
  • Evaluation of phytoremediation treatability studies in former disposal areas to assist in the removal of contamination from groundwater; and
  • Implementation of institutional controls to protect the integrity of the remedial action components.

In 2009, EPA initiated a fourth removal action to address high concentrations of trichloroethene, also known as trichloroethylene or TCE, in indoor air at the single-family residence on the site through a migration pathway known as “vapor intrusion.” Vapor intrusion occurs when organic hazardous substances, such as TCE, volatilize from the dissolved phase in groundwater into the gaseous phase and migrate upward and into overlying structures. The residence is located within the Former Source Area, a region about 20 or 25 acres in size in the central part of the Site where the releases of hazardous substances occurred and concentrations of contaminants of concern (COCs) in groundwater remain high. Groundwater contaminated with high concentrations of TCE enters two sumps in the basement, and for reasons largely related to the older construction of the residence, accumulates in basement air and subsequently, the indoor air of the living space above. TCE is one of 19 COCs selected in the remedy, and presents an acute risk at low concentrations in indoor air. Measures taken between 2009 and 2014 significantly reduced the concentrations of TCE in indoor air of the residence, but a potential risk may still exist for women of child-bearing years in certain conditions. In January 2019, EPA completed upgrades to basement sumps and an air exhaust system that successfully mitigated TCE concentrations in indoor air to acceptable risk levels.

EPA has also overseen upgrades made by the parties performing the cleanup to the existing groundwater extraction and treatment system.  The first phase of upgrades began in 2017.  As part of this phase, the larger of the two man-made ponds was drained to permit more effective control of groundwater.  Afterward, a second interceptor trench was installed and additional extraction wells were drilled to address incomplete capture from former source areas at the origin of the Southern Plume.  The land was regraded to reflect the original drainage patterns and Eastern cottonwoods were planted to promote the restoration of the land as a wooded wetland.  The second phase will address potential incomplete capture near the origins of the Northern and Access Road plumes.  This work is scheduled to begin in November 2019.

 

 

 

 

 

 

 

 

 

 

Top of Page


What Is the Current Site Status?

A group of potentially responsible parties (PRPs) is performing operation and maintenance of the remedy through an agreement with the United States Government (these are the same parties described in the previous section).  EPA conducts oversight of all PRP activities at the site.  Maintenance of the groundwater extraction and treatment system is conducted on an on-going basis.  Sampling of monitoring wells and some residential potable wells near the site occurs on a semi-annual basis.  The PRPs perform annual indoor air and sub-slab vapor sampling at two off-site residences.

EPA completed the third five-year review (PDF) in September 2017 of the long-term cleanup action, also known as the remedial action or remedy for the site.  The review declared the remedy “not protective of human health” due to a potential for unacceptable risks in the residence on the site.  However, the critical issue causing that declaration – high concentration of TCE in the indoor air of the on-site residence – was addressed through the EPA-lead removal action in 2018 (more information on the removal action can be found at the EPA On-Scene Coordinator webpage for the site).  The remedy is now protective of human health and the environment.  Note that the remedy has always been protective of human health and the environment for other potential receptors and media (soil, surface water, groundwater, indoor air) on and off the site since inception of the remedial action in the early 2000s. 

 

 

 

 

 

Top of Page


Emergency Response and Removal

Site cleanup has included removal actions, or short-term cleanups, to address immediate threats to human health and the environment as EPA became aware of the threats. All removal actions have been completed. These actions included:

  • removal of over 2,500 drums and numerous tanker trucks from the site;
  • construction of a groundwater collection and treatment system;
  • installation of extraction wells, an interceptor trench and residential well treatment filters;
  • identification, excavation and removal of drums and soils contaminated with radioactive waste; and
  • mitigation of high concentrations of TCE vapors in indoor air of the on-site residence.   

 

 

 

Top of Page