Superfund Information Systems: Site Profile

Superfund Site:

CAMP LEJEUNE MILITARY RES. (USNAVY)
ONSLOW COUNTY, NC

Operable Units

Below, EPA has provided a list of the remedial actions selected pertaining to each operable unit.

EPA issues Records of Decision (RODs) to explain which cleanup methods will be used at Superfund National Priorities List sites. EPA has two primary documents that it may use to identify changes to the remedies selected in RODs. EPA uses a ROD Amendment when it needs to make a fundamental change to the remedy. EPA publishes an Explanation of Significant Differences (ESD) for significant changes.

During cleanup, complex sites may be divided into several distinct areas to make the response more efficient. These areas, called operable units (OUs), may address geographic areas, specific problems, or medium (e.g., groundwater, soil) where a specific action is required. The remedies are displayed for the OU numbers indicated in the original decision document. OU numbers may change over time.

EPA is working to improve data quality. The information presented on this page is undergoing review for accuracy and completeness, and may be subject to change.

OU ID Name Decision Document Cleanup Technologies Selected
in the Decision Document
00 SITEWIDE Not applicable
01 SHALLOW ACQUIFER (HPIA) Record of Decision
September 23, 1992
Air Stripping (P&T, exsitu)
Carbon Adsorption (liquid phase, P&T, exsitu)
Chemical Reduction (insitu)
Clarification (sedimentation, P&T, exsitu)
Discharge (POTW)
Extraction (recovery/vertical well)
Institutional Controls
Monitoring
Oil Water Separation (P&T, exsitu)
Precipitation (P&T, exsitu)
02 SITE 21, 24, 78 (HIPA) Record of Decision
September 15, 1994
Disposal
Excavation
Institutional Controls
Monitoring
Other (NOS)
Treatment (other, NOS, exsitu, onsite)
02 SITE 21, 24, 78 (HIPA) Explanation of Significant Differences
April 04, 2017
ESD/Amd - COC(s) Change
ESD/Amd - Cleanup/Performance Standard Change
ESD/Amd - ICs - Implement or Change
ESD/Amd - RAO(s) Change
Institutional Controls
Sampling
Sub-Slab Depressurization (SSD) (for VI mitigation)
03 SITE 6, 9, & 82 Record of Decision
September 24, 1993
Air Stripping (P&T, exsitu)
Carbon Adsorption (liquid phase, P&T, exsitu)
Discharge (surface water/NPDES discharge)
Disposal (offsite)
Excavation
Filtration (P&T, exsitu)
Institutional Controls
Neutralization (P&T, exsitu)
Precipitation (P&T, exsitu)
Soil Vapor Extraction (insitu)
Treatment (other, NOS, exsitu, onsite)
03 SITE 6, 9, & 82 Explanation of Significant Differences
April 04, 2017
ESD/Amd - COC(s) Change
ESD/Amd - Cleanup/Performance Standard Change
ESD/Amd - ICs - Implement or Change
ESD/Amd - RAO(s) Change
Institutional Controls
04 SITE 48 Record of Decision
September 10, 1993
Data not available
05 SITE 74, 41 Record of Decision
December 05, 1995
Institutional Controls
Monitoring
06 SITE 2 Record of Decision
September 15, 1994
Institutional Controls
Monitoring
07 SITES 36,43,44,54 Record of Decision
July 06, 2005
Institutional Controls
Monitored Natural Attenuation
Monitoring
No Action
07 SITES 36,43,44,54 Explanation of Significant Differences
April 04, 2017
ESD/Amd - COC(s) Change
ESD/Amd - Cleanup/Performance Standard Change
ESD/Amd - RAO(s) Change
Institutional Controls
08 SITES 1, 28,& 30 Record of Decision
October 09, 1996
COC Only
Institutional Controls
Monitored Natural Attenuation
Monitoring (groundwater)
No Action
09 SITE 16 Record of Decision
August 23, 1996
No Further Action
10 SITE 65 Record of Decision
September 28, 2001
No Action
11 SITE 35 Record of Decision
September 15, 1994
Excavation
Recycling (offsite)
Revegetation
Sampling
Storage (temporary, onsite)
11 SITE 35 Record of Decision
September 22, 1995
Aeration Basin (P&T, exsitu)
Carbon Adsorption (liquid phase, P&T, exsitu)
Institutional Controls
Monitoring
11 SITE 35 Record of Decision
November 16, 2009
Air Sparging (physical treatment, insitu)
Institutional Controls
Monitored Natural Attenuation
Monitoring
11 SITE 35 Explanation of Significant Differences
April 04, 2017
ESD/Amd - RAO(s) Change
Institutional Controls
12 SITE 7 & 80 Record of Decision
January 20, 1998
No Action
No Further Action
12 SITE 7 & 80 Record of Decision
October 16, 2012
Institutional Controls
13 SITE 3 Record of Decision
May 15, 1997
Bioremediation (other, NOS, exsitu)
Excavation
Institutional Controls
Monitoring
13 SITE 3 Record of Decision Amendment
June 20, 2000
Containment (other, NOS, onsite)
Excavation
Monitoring
Sampling
14 SITE 63 Record of Decision
May 15, 1997
Institutional Controls
No Further Action
15 SITE 69 Record of Decision
September 27, 2000
Institutional Controls
Monitored Natural Attenuation
Monitoring
15 SITE 69 Record of Decision
June 25, 2013
Cap (engineered cap)
Drainage/Erosion Control (dike/berm/levee)
Institutional Controls
Monitored Natural Attenuation
No Further Action
16 SITE 88 Record of Decision
May 23, 2019
Data not available
17 SITE 89, 93 Record of Decision
October 02, 2006
Chemical Oxidation (insitu)
Institutional Controls
Monitored Natural Attenuation
Monitoring
No Action
17 SITE 89, 93 Record of Decision
December 16, 2012
Aeration (insitu)
Air Sparging (physical treatment, insitu)
Institutional Controls
Monitored Natural Attenuation
Monitoring (groundwater)
Monitoring (surface water)
Permeable Reactive Barrier (chemical reactive wall, passive treatment wall, etc.)
18 SITE 90, 91, 92 Record of Decision
September 28, 2001
No Action
19 SITE 94 Record of Decision
August 28, 2006
No Further Action
20 SITE 84 Record of Decision
January 21, 2009
Institutional Controls
Operations & Maintenance (O&M)
21 SITE 86 Record of Decision
October 29, 2014
Institutional Controls
Monitored Natural Attenuation
22 SITE 73 Record of Decision
December 01, 2009
Air Sparging (physical treatment, insitu)
Bioremediation (anaerobic, insitu)
Discharge (surface water/NPDES discharge)
Institutional Controls
Monitored Natural Attenuation
Monitoring
22 SITE 73 Explanation of Significant Differences
April 04, 2017
ESD/Amd - RAO(s) Change
Institutional Controls
23 UXO-22 Explanation of Significant Differences
April 04, 2017
Data not available
24 SITE 49 Record of Decision
April 24, 2014
Institutional Controls
Monitored Natural Attenuation
25 SITE UXO-06 Record of Decision
April 30, 2018
Data not available
27 UXO-19 Record of Decision
December 09, 2015
Institutional Controls
28 UXO-23 No decision document
29 UXO-24 SITE 37 (OU26) Record of Decision
September 30, 2019
Data not available
30 UXO-28 (OU30) No decision document
31 UXO-29 (OU31) No decision document
32 SITE 96 (OU22) No decision document

Top of Page