Superfund Information Systems: Site Profile

Superfund Site:

CONTINENTAL STEEL CORP.
KOKOMO, IN

Operable Units

Below, EPA has provided a list of the remedial actions selected pertaining to each operable unit.

EPA issues Records of Decision (RODs) to explain which cleanup methods will be used at Superfund National Priorities List sites. EPA has two primary documents that it may use to identify changes to the remedies selected in RODs. EPA uses a ROD Amendment when it needs to make a fundamental change to the remedy. EPA publishes an Explanation of Significant Differences (ESD) for significant changes.

During cleanup, complex sites may be divided into several distinct areas to make the response more efficient. These areas, called operable units (OUs), may address geographic areas, specific problems, or medium (e.g., groundwater, soil) where a specific action is required.

EPA is working to improve data quality. The information presented on this page is undergoing review for accuracy and completeness, and may be subject to change.

OU ID Name Decision Document Cleanup Technologies Selected
in the Decision Document
00 SITEWIDE No decision document
01 GROUNDWATER Record of Decision
September 30, 1998
Data not available
01 GROUNDWATER Record of Decision Amendment
September 26, 2003
Data not available
01 GROUNDWATER Explanation of Significant Differences
September 30, 2005
Cap (engineered cap)
Disposal (offsite)
ESD/Amd - Remedy Element Addition/Modification
Soil Vapor Extraction (insitu)
02 LAGOON AREA Record of Decision
September 30, 1998
No Further Action
02 LAGOON AREA Explanation of Significant Differences
September 21, 2010
Consolidate (onsite)
Cover (soil)
Demolition
Disposal (offsite)
Excavation
Institutional Controls
Slope Stabilization
03 CREEKS (WILDCAT & KOKOMO) Record of Decision
September 30, 1998
No Further Action
04 MARKLAND AVE QUARRY Record of Decision
September 30, 1998
No Further Action
05 MAIN PLANT Record of Decision
August 16, 1996
Containment (other, NOS, onsite)
Decontamination
Disposal (offsite)
Excavation
Institutional Controls
Other (NOS)
Physical Separation (exsitu, onsite)
Recycling (onsite)
05 MAIN PLANT Record of Decision
September 30, 1998
Disposal
05 MAIN PLANT Explanation of Significant Differences
September 21, 2010
Consolidate (onsite)
Cover (soil)
Excavation
Institutional Controls
06 SLAG AREA/CHAFFIN QUARRY Record of Decision
September 30, 1998
No Further Action
07 DIXON ROAD QUARRY No decision document

Top of Page