Superfund Site:

COAKLEY LANDFILL
NORTH HAMPTON, NH

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 07/01/1983
Proposed to the National Priorities List 10/15/1984
Finalized on the National Priorities List 06/10/1986
Remedy Selected 06/28/1990
Final Remedy Selected 09/30/1994
Remedial Action Started 01/25/1996
Construction Completed 09/29/1999
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/26/2016
Site Ready for Reuse and Redevelopment 03/23/2011

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 09/21/2006 00
Five-Year Review OU 00 - SITEWIDE 09/22/2011 00
Five-Year Review OU 00 - SITEWIDE 09/25/2001 00
Five-Year Review OU 00 - SITEWIDE 09/26/2016 00
Combined Remedial Investigation/Feasibility Study OU 01 - SOURCE 08/29/1985 06/28/1990 01
Record of Decision OU 01 - SOURCE 06/28/1990 01
Remedial Design OU 01 - SOURCE 06/19/1992 01/25/1996 01
Remedial Action OU 01 - SOURCE 01/25/1996 03/08/2000 01
Operation and Maintenance OU 01 - SOURCE 09/29/1999 01
Combined Remedial Investigation/Feasibility Study OU 02 - OFFSITE GW 09/27/1990 09/30/1994 02
Record of Decision OU 02 - OFFSITE GW 09/30/1994 02
Remedial Design OU 02 - OFFSITE GW 10/23/1998 03/10/1999 02
Remedial Action OU 02 - OFFSITE GW 03/10/1999 03/08/2000 02
Long-Term Response Action OU 02 - OFFSITE GW 03/08/2000 02

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.