Superfund Information Systems: Site Profile

Superfund Site:

PRICE LANDFILL
PLEASANTVILLE, NJ

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 11/01/1979
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 01/06/1982
Remedy Selected 09/20/1983
Final Remedy Selected 09/29/1986
Remedial Action Started 10/27/1983
Final Remedial Action Started Estimated Jul - Sep 2021
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Consent Decree (EPA Performed) OU 00 - SITEWIDE 06/30/1988 00
Removal (EPA Performed) OU 00 - SITEWIDE 04/09/1982 Estimated Mar - May 2016 00
Removal (EPA Performed) OU 00 - SITEWIDE 06/18/1982 Estimated Mar - May 2016 00
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - WATER SUPPLY 01/06/1982 09/20/1983 01
Record of Decision (EPA Performed) OU 01 - WATER SUPPLY 09/20/1983 01
Remedial Design (EPA Performed) OU 01 - WATER SUPPLY 09/29/1983 10/27/1983 01
Remedial Action (State Performed) OU 01 - WATER SUPPLY 10/27/1983 12/17/1985 01
Combined Remedial Investigation/Feasibility Study (State Performed) OU 02 - GW AND CAP 06/18/1984 09/29/1986 02
Record of Decision (State Performed) OU 02 - GW AND CAP 09/29/1986 02
Remedial Design (State Performed) OU 02 - GW AND CAP 06/26/1987 07/30/1988 02
Remedial Design (State Performed) OU 02 - GW AND CAP 07/01/1995 12/01/1999 02
Remedial Design (State Performed) OU 02 - GW AND CAP 06/30/2002 02/03/2009 02
Remedial Design (EPA Performed) OU 02 - GW AND CAP 02/03/2009* 09/29/2010 02
Remedial Design (EPA Performed) OU 02 - GW AND CAP 02/03/2009* 10/26/2011 02
Remedial Design (EPA Performed) OU 02 - GW AND CAP 08/24/2011 Estimated Jul - Sep 2021 02
Remedial Action (State Performed) OU 02 - GW AND CAP 12/01/1999 02/01/2002 02
Remedial Action (EPA Performed) OU 02 - GW AND CAP 06/03/2009 09/17/2014 02
Remedial Action (EPA Performed) OU 02 - GW AND CAP 09/10/2012 09/25/2015 02
Remedial Action OU 02 - GW AND CAP Estimated Jul - Sep 2021 02
Long-Term Response Action (EPA Performed) OU 02 - GW AND CAP 09/30/2014 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.

Top of Page