Superfund Information Systems: Site Profile

Superfund Site:

CHEMICAL INSECTICIDE CORP.
EDISON TOWNSHIP, NJ

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 12/01/1985
Proposed to the National Priorities List 10/26/1989
Finalized on the National Priorities List 08/30/1990
Remedy Selected 09/29/1989
Final Remedy Selected 12/22/2003
Remedial Action Started 09/28/1990
Remedy Construction Completed 09/16/2005
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/23/2014
Site Ready for Reuse and Redevelopment 09/10/2012

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 02/16/1988 02/26/1988 00
Removal OU 00 - SITEWIDE 03/07/1989 03/13/1989 00
Removal OU 00 - SITEWIDE 04/07/1994 05/09/1994 00
Removal OU 00 - SITEWIDE 06/02/1993 06/04/1993 00
Removal OU 00 - SITEWIDE 06/08/1994 06/08/1994 00
Removal OU 00 - SITEWIDE 09/13/1990 09/21/1990 00
Five-Year Review OU 00 - SITEWIDE 03/10/2009 00
Five-Year Review OU 00 - SITEWIDE 06/18/1998 00
Five-Year Review OU 00 - SITEWIDE 09/23/2014 00
Five-Year Review OU 00 - SITEWIDE 12/29/2003 00
Combined Remedial Investigation/Feasibility Study OU 01 - INTERIM REMEDY: SW RUNOFF 03/29/1985 09/29/1989 01
Record of Decision OU 01 - INTERIM REMEDY: SW RUNOFF 09/29/1989 01
Remedial Design OU 01 - INTERIM REMEDY: SW RUNOFF 09/30/1989 12/31/1991 01
Remedial Action OU 01 - INTERIM REMEDY: SW RUNOFF 09/28/1990 07/31/1995 01
Combined Remedial Investigation/Feasibility Study OU 02 - SOIL REMEDY 03/29/1985 09/29/2000 02
Record of Decision OU 02 - SOIL REMEDY 09/29/2000 02
Remedial Design OU 02 - SOIL REMEDY 09/29/2000 11/04/2003 02
Remedial Action OU 02 - SOIL REMEDY 09/30/2002 09/28/2007 02
Combined Remedial Investigation/Feasibility Study OU 03 - OFF-SITE REMEDY:CREEK/BROOK 12/03/1993 03/28/1995 03
Record of Decision OU 03 - OFF-SITE REMEDY:CREEK/BROOK 03/28/1995 03
Remedial Design OU 03 - OFF-SITE REMEDY:CREEK/BROOK 05/30/1995 06/01/1996 03
Remedial Action OU 03 - OFF-SITE REMEDY:CREEK/BROOK 06/16/1995 08/18/1995 03
Remedial Action OU 03 - OFF-SITE REMEDY:CREEK/BROOK 09/13/1995 07/01/1997 03
Combined Remedial Investigation/Feasibility Study OU 04 - GROUNDWATER 12/03/1993 12/22/2003 04
Record of Decision OU 04 - GROUNDWATER 12/22/2003 04

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.