SHARKEY LANDFILL
PARSIPPANY, TROY HLS, NJ

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 08/01/1982
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 12/30/1983
Final Remedy Selected 09/29/1986
Final Remedial Action Started 05/09/2000
Construction Completed 03/09/2004
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/30/2019
Site Ready for Reuse and Redevelopment 03/22/2013

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Consent Decree (EPA Performed) OU 00 - SITEWIDE 01/28/1999 00
Removal (EPA Performed) OU 00 - SITEWIDE 02/28/1992 04/21/1992 00
Removal (EPA Performed) OU 00 - SITEWIDE 07/01/1992 07/15/1992 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 05/26/2009 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/29/2014 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/30/2019 00
Consent Decree (EPA Performed) OU 01 - CONTAINMENT CAP/GROUNDWATER 12/02/1994 01
Combined Remedial Investigation/Feasibility Study (State Performed) OU 01 - CONTAINMENT CAP/GROUNDWATER 12/30/1983 09/29/1986 01
Record of Decision (State Performed) OU 01 - CONTAINMENT CAP/GROUNDWATER 09/29/1986 01
Remedial Design (State Performed) OU 01 - CONTAINMENT CAP/GROUNDWATER 03/31/1987 04/29/1994* 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - CONTAINMENT CAP/GROUNDWATER 10/18/1994 05/09/2000 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - CONTAINMENT CAP/GROUNDWATER 05/09/2000 09/29/2005 01
Operation and Maintenance (State Performed) OU 01 - CONTAINMENT CAP/GROUNDWATER 09/29/2005 01

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.