Superfund Information Systems: Site Profile

Superfund Site:

LIBERTY INDUSTRIAL FINISHING
FARMINGDALE, NY

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 09/01/1984
Proposed to the National Priorities List 10/15/1984
Finalized on the National Priorities List 06/10/1986
Remedial Investigation Started 04/17/1985
Remedy Selected 03/28/2002
Final Remedy Selected 09/27/2012
Remedial Action Started 08/10/2006
Final Remedial Action Started 09/30/2008
Construction Completed 09/28/2012
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 07/18/2017
Site Ready for Reuse and Redevelopment 02/10/2014

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 08/30/1994 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 03/27/2002 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 03/03/1992 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 08/30/1994 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 08/03/1998 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/23/1994 04/24/1996 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/25/1998 08/27/2004 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 03/27/2002 08/27/2004 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 06/04/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 07/18/2017 00
Five-Year Review OU 00 - SITEWIDE Estimated Jul - Sep 2022 00
Administrative Order of Consent (EPA Performed) OU 01 - ENTIRE SITE 01/24/1997 01
Consent Decree (EPA Performed) OU 01 - ENTIRE SITE 08/27/2004 01
Unilateral Administrative Order (EPA Performed) OU 01 - ENTIRE SITE 01/24/1997 01
Combined Remedial Investigation/Feasibility Study (State Oversight) OU 01 - ENTIRE SITE 04/17/1985 09/28/1990 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - ENTIRE SITE 09/28/1990* 03/28/2002 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 01/24/1997* 03/28/2002 01
Record of Decision (EPA Performed) OU 01 - ENTIRE SITE 03/28/2002 01
Record of Decision Amendment (EPA Performed) OU 01 - ENTIRE SITE 09/27/2012 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/30/2003 08/10/2006 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/30/2003 09/27/2007 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/30/2003 09/30/2008 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 08/10/2006 09/30/2010 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/27/2007 03/31/2009 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/30/2008 09/29/2011 01
Long-Term Response Action (PRP Performed, EPA Oversight) OU 01 - ENTIRE SITE 09/29/2011 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 02 - OU02 09/30/1995 01/24/1997* 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.