Superfund Information Systems: Site Profile

Superfund Site:

FACET ENTERPRISES, INC.
ELMIRA, NY

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 02/01/1980
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 05/22/1986
Final Remedy Selected 09/04/1992
Remedial Action Started 05/14/1996
Construction Completed 06/30/2000
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/28/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal (EPA Performed) OU 00 - SITEWIDE 09/26/2007 09/21/2011 00
Removal (EPA Performed) OU 00 - SITEWIDE 01/29/2014 08/16/2017 00
Removal (EPA Performed) OU 00 - SITEWIDE 08/29/2017 Estimated Sep - Nov 2020 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 11/09/2001 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/28/2007 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/28/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/28/2017 00
Five-Year Review OU 00 - SITEWIDE Estimated Sep - Nov 2022 00
Administrative Order of Consent (EPA Performed) OU 01 - RI/FS AND RD/RA 04/08/1983 01
Administrative Order of Consent (EPA Performed) OU 01 - RI/FS AND RD/RA 05/22/1986 01
Consent Decree (EPA Performed) OU 01 - RI/FS AND RD/RA 06/17/1993 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - RI/FS AND RD/RA 05/22/1986 09/04/1992 01
Record of Decision (EPA Performed) OU 01 - RI/FS AND RD/RA 09/04/1992 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - RI/FS AND RD/RA 05/25/1993 05/14/1996 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - RI/FS AND RD/RA 05/14/1996 09/29/2000 01
Long-Term Response Action (PRP Performed, EPA Oversight) OU 01 - RI/FS AND RD/RA 09/29/2000 09/29/2010 01
Operation and Maintenance OU 01 - RI/FS AND RD/RA Estimated Aug - Oct 2015 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 02 - OFF PROPERTY GW 04/24/2018 02

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.