Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 07/01/1987
Proposed to the National Priorities List 09/25/1997
Finalized on the National Priorities List 03/06/1998
Remedy Selected 09/30/2005
Remedial Action Started 10/15/2009
Construction Completed 09/17/2010
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 04/01/2015
Site Ready for Reuse and Redevelopment 07/08/2016

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 10/24/1996 04/22/1997 00
Five-Year Review OU 00 - SITEWIDE 04/01/2015 00
Combined Remedial Investigation/Feasibility Study OU 01 - ENTIRE SITE 05/08/2000 01
Combined Remedial Investigation/Feasibility Study OU 01 - ENTIRE SITE 09/30/1998 05/08/2000 01
Record of Decision OU 01 - ENTIRE SITE 09/30/2005 01
Remedial Design OU 01 - ENTIRE SITE 09/11/2008 10/15/2009 01
Remedial Action OU 01 - ENTIRE SITE 10/15/2009 06/17/2011 01

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.