Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 04/22/1990
Proposed to the National Priorities List 05/10/1993
Finalized on the National Priorities List 12/16/1994
Remedy Selected 02/09/1998
Remedial Action Started 07/15/1999
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/07/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 01/17/2012 00
Five-Year Review OU 00 - SITEWIDE 01/30/2007 00
Five-Year Review OU 00 - SITEWIDE 04/27/2017 00
Five-Year Review OU 00 - SITEWIDE 05/20/2016 00
Five-Year Review OU 00 - SITEWIDE 05/24/2017 00
Five-Year Review OU 00 - SITEWIDE 09/07/2017 00
Five-Year Review OU 00 - SITEWIDE 09/24/2015 00
Five-Year Review OU 00 - SITEWIDE 09/25/2015 00
Five-Year Review OU 00 - SITEWIDE 10/08/2009 00
Five-Year Review OU 00 - SITEWIDE 10/08/2014 00
Remedial Investigation OU 01 - SITEWIDE RESPONSE 09/27/2000 10/02/2008 01
Combined Remedial Investigation/Feasibility Study OU 01 - SITEWIDE RESPONSE 09/30/1994 01
Feasibility Study OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 07/01/2005 02
Combined Remedial Investigation/Feasibility Study OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 03/16/1992 07/01/2005 02
Record of Decision OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 07/01/2005 02
Remedial Design OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 01/04/2007 04/25/2011 02
Remedial Design OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 01/04/2007 05/08/2012 02
Remedial Design OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 01/04/2007 09/21/2011 02
Remedial Action OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 04/14/2012 02
Remedial Action OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 05/24/2011 02
Remedial Action OU 02 - ONONDAGA LAKE BOTTOMS SUBSITE 07/21/2010 02
Combined Remedial Investigation/Feasibility Study OU 03 - WILLIS AVE. SUBSITE CB CONTAM. 08/10/1990 03
Combined Remedial Investigation/Feasibility Study OU 05 - LCP BRIDGE STREET SUBSITE 10/20/1995 09/29/2000 05
Record of Decision OU 05 - LCP BRIDGE STREET SUBSITE 09/29/2000 05
Remedial Design OU 05 - LCP BRIDGE STREET SUBSITE 08/23/2001 06/10/2014 05
Remedial Design OU 05 - LCP BRIDGE STREET SUBSITE 08/23/2001 09/30/2004 05
Remedial Action OU 05 - LCP BRIDGE STREET SUBSITE 06/10/2014 09/15/2016 05
Remedial Action OU 05 - LCP BRIDGE STREET SUBSITE 09/30/2004 11/13/2012 05
Remedial Action OU 05 - LCP BRIDGE STREET SUBSITE 09/30/2004 05
Combined Remedial Investigation/Feasibility Study OU 06 - SEMET RESIDUE PONDS SUBSITE 06/26/1989 03/28/2002 06
Record of Decision OU 06 - SEMET RESIDUE PONDS SUBSITE 03/28/2002 06
Remedial Design OU 06 - SEMET RESIDUE PONDS SUBSITE 10/20/2004 12/04/2009 06
Remedial Action OU 06 - SEMET RESIDUE PONDS SUBSITE 12/04/2009 06
Combined Remedial Investigation/Feasibility Study OU 07 - MAESTRI II SUBSITE 01/25/2000 07
Combined Remedial Investigation/Feasibility Study OU 08 - SALINA LANDFILL SUBSITE 11/11/1997 03/29/2007 08
Record of Decision OU 08 - SALINA LANDFILL SUBSITE 03/29/2007 08
Record of Decision Amendment OU 08 - SALINA LANDFILL SUBSITE 09/30/2010 08
Remedial Design OU 08 - SALINA LANDFILL SUBSITE 06/10/2007 12/23/2013 08
Remedial Design OU 08 - SALINA LANDFILL SUBSITE 07/10/2007 08/12/2010 08
Remedial Action OU 08 - SALINA LANDFILL SUBSITE 08/12/2010 10/01/2014 08
Remedial Action OU 08 - SALINA LANDFILL SUBSITE 12/13/2013 11/03/2015 08
Combined Remedial Investigation/Feasibility Study OU 09 - GENERAL MOTORS INLAND FISHER 09/27/1997 03/31/2015 09
Record of Decision OU 09 - GENERAL MOTORS INLAND FISHER 03/31/2015 09
Remedial Design OU 09 - GENERAL MOTORS INLAND FISHER 08/17/2015 06/09/2017 09
Remedial Action OU 09 - GENERAL MOTORS INLAND FISHER 10/21/2016 09
Feasibility Study OU 10 - LEY CREEK PCB DREDGINGS SUBSIT 10/01/1993 02/09/1998 10
Record of Decision OU 10 - LEY CREEK PCB DREDGINGS SUBSIT 02/09/1998 10
Remedial Design OU 10 - LEY CREEK PCB DREDGINGS SUBSIT 02/09/1998 07/15/1999 10
Remedial Action OU 10 - LEY CREEK PCB DREDGINGS SUBSIT 07/15/1999 09/28/2001 10
Combined Remedial Investigation/Feasibility Study OU 11 - AMERICAN BAG AND METAL 03/16/2010 11
Combined Remedial Investigation/Feasibility Study OU 13 - NIAGARA MOHAWK - HIAWATHA BLV 09/29/1999 03/31/2010 13
Record of Decision OU 13 - NIAGARA MOHAWK - HIAWATHA BLV 03/31/2010 13
Remedial Design OU 13 - NIAGARA MOHAWK - HIAWATHA BLV 04/01/2010 09/28/2011 13
Remedial Design OU 13 - NIAGARA MOHAWK - HIAWATHA BLV 04/01/2010 13
Remedial Action OU 13 - NIAGARA MOHAWK - HIAWATHA BLV 09/28/2011 09/27/2013 13
Combined Remedial Investigation/Feasibility Study OU 14 - NIAGARA MOHAWK - ERIE BLVD 11/08/1999 14
Combined Remedial Investigation/Feasibility Study OU 16 - LCP/NAKOH 05/24/2002 16
Combined Remedial Investigation/Feasibility Study OU 18 - HARBOR BROOK/WASTEBED B 11/08/2002 18
Combined Remedial Investigation/Feasibility Study OU 19 - WILLIS AVENUE BALLFIELD 11/01/2002 19
Removal OU 20 - GEDDES BROOK/NINEMILE CREEK 04/25/2011 20
Combined Remedial Investigation/Feasibility Study OU 20 - GEDDES BROOK/NINEMILE CREEK 01/22/1998 04/29/2009 20
Record of Decision OU 20 - GEDDES BROOK/NINEMILE CREEK 04/29/2009 20
Remedial Design OU 20 - GEDDES BROOK/NINEMILE CREEK 12/31/2010 09/13/2013 20
Remedial Action OU 20 - GEDDES BROOK/NINEMILE CREEK 03/22/2012 10/05/2016 20
Combined Remedial Investigation/Feasibility Study OU 22 - WASTEBEDS 1-8 10/04/2005 12/02/2014 22
Record of Decision OU 22 - WASTEBEDS 1-8 12/02/2014 22
Remedial Design OU 22 - WASTEBEDS 1-8 05/08/2015 06/30/2015 22
Remedial Design OU 22 - WASTEBEDS 1-8 05/08/2015 07/06/2015 22
Remedial Action OU 22 - WASTEBEDS 1-8 06/30/2015 22
Remedial Action OU 22 - WASTEBEDS 1-8 07/06/2015 22
Combined Remedial Investigation/Feasibility Study OU 24 - LOWER NINEMILE CR REACHES A-B 01/22/1998 10/01/2009 24
Record of Decision OU 24 - LOWER NINEMILE CR REACHES A-B 10/01/2009 24
Remedial Design OU 24 - LOWER NINEMILE CR REACHES A-B 12/31/2010 09/13/2013 24
Remedial Action OU 24 - LOWER NINEMILE CR REACHES A-B 09/13/2013 10/05/2016 24
Combined Remedial Investigation/Feasibility Study OU 25 - LOWER LEY CREEK 10/27/2009 09/30/2014 25
Record of Decision OU 25 - LOWER LEY CREEK 09/30/2014 25
Remedial Design OU 25 - LOWER LEY CREEK 07/21/2016 25
Combined Remedial Investigation/Feasibility Study OU 26 - IFG SUBSITE - FORMER PLANT AND GROUNDWATER 09/27/1997 26

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.