Superfund Information Systems: Site Profile

Superfund Site:

FEDERAL CREOSOTE
MANVILLE, NJ

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed Not Yet Achieved
Proposed to the National Priorities List 07/28/1998
Finalized on the National Priorities List 01/19/1999
Remedy Selected 09/28/1999
Final Remedy Selected 09/30/2002
Remedial Action Started 09/30/1999
Construction Completed 03/31/2008
Deleted from National Priorities List 06/18/2014
Most Recent Five-Year Review 01/20/2017
Site Ready for Reuse and Redevelopment 10/30/2013

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 07/28/1998 09/15/1998 00
Five-Year Review OU 00 - SITEWIDE 01/20/2017 00
Five-Year Review OU 00 - SITEWIDE 05/03/2012 00
Five-Year Review OU 00 - SITEWIDE 06/07/2007 00
Feasibility Study OU 01 - SOILS/RELOCATION 05/28/1998 09/28/1999 01
Combined Remedial Investigation/Feasibility Study OU 01 - SOILS/RELOCATION 08/10/1998 09/28/1999 01
Record of Decision OU 01 - SOILS/RELOCATION 09/28/1999 01
Remedial Design OU 01 - SOILS/RELOCATION 09/30/1999 02/05/2003 01
Remedial Design OU 01 - SOILS/RELOCATION 09/30/1999 03/15/2002 01
Remedial Design OU 01 - SOILS/RELOCATION 09/30/1999 10/11/2000 01
Remedial Design OU 01 - SOILS/RELOCATION 09/30/1999 11/12/2000 01
Remedial Action OU 01 - SOILS/RELOCATION 01/31/2002 08/28/2008 01
Remedial Action OU 01 - SOILS/RELOCATION 03/18/2003 09/28/2006 01
Remedial Action OU 01 - SOILS/RELOCATION 07/31/2000 08/22/2005 01
Remedial Action OU 01 - SOILS/RELOCATION 09/30/1999 09/28/2007 01
Combined Remedial Investigation/Feasibility Study OU 02 - SITEWIDE SOILS 08/14/1998 04/28/2000 02
Record of Decision OU 02 - SITEWIDE SOILS 09/29/2000 02
Remedial Design OU 02 - SITEWIDE SOILS 09/29/2000 04/01/2003 02
Remedial Design OU 02 - SITEWIDE SOILS 09/29/2000 07/15/2001 02
Remedial Design OU 02 - SITEWIDE SOILS 09/29/2000 12/02/2001 02
Remedial Action OU 02 - SITEWIDE SOILS 04/18/2002 08/22/2005 02
Remedial Action OU 02 - SITEWIDE SOILS 05/14/2003 09/28/2006 02
Remedial Action OU 02 - SITEWIDE SOILS 08/06/2001 09/28/2006 02
Combined Remedial Investigation/Feasibility Study OU 03 - RUSTIC MALL & GROUNDWATER 09/30/1998 09/30/2002 03
Record of Decision OU 03 - RUSTIC MALL & GROUNDWATER 09/30/2002 03
Remedial Design OU 03 - RUSTIC MALL & GROUNDWATER 09/30/2002 09/30/2004 03
Remedial Action OU 03 - RUSTIC MALL & GROUNDWATER 08/23/2004 08/28/2008 03

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.