Superfund Information Systems: Site Profile

Superfund Site:

JACKSON STEEL
MINEOLA/NORTH HEMPSTEAD, NY

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 07/01/1999
Proposed to the National Priorities List 10/22/1999
Finalized on the National Priorities List 02/04/2000
Remedial Investigation Started 09/01/2000
Final Remedy Selected 09/24/2004
Remedial Action Started 09/08/2005
Final Remedial Action Started 09/14/2005
Construction Completed 08/30/2007
Deleted from National Priorities List 09/26/2016
Most Recent Five-Year Review 05/18/2017
Site Ready for Reuse and Redevelopment 07/27/2016

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal (EPA Performed) OU 00 - SITEWIDE 02/02/2002 03/21/2002 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 08/15/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 05/18/2017 00
Five-Year Review OU 00 - SITEWIDE Estimated May - Jul 2022 00
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - ENTIRE SITE 09/01/2000 09/24/2004 01
Record of Decision (EPA Performed) OU 01 - ENTIRE SITE 09/24/2004 01
Explanation of Significant Differences (EPA Performed) OU 01 - ENTIRE SITE 08/28/2007 01
Explanation of Significant Differences (EPA Performed) OU 01 - ENTIRE SITE 06/20/2016 01
Remedial Design (EPA Performed) OU 01 - ENTIRE SITE 09/29/2004 08/27/2007 01
Remedial Action (EPA Performed) OU 01 - ENTIRE SITE 09/08/2005 09/30/2008 01
Remedial Action (EPA Performed) OU 01 - ENTIRE SITE 09/14/2005 09/29/2006 01

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.