Superfund Information Systems: Site Profile

Superfund Site:

C & D RECYCLING
FOSTER TOWNSHIP, PA

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 04/04/1985
Proposed to the National Priorities List 09/18/1985
Finalized on the National Priorities List 07/22/1987
Remedial Investigation Started 08/31/1987
Final Remedy Selected 09/30/1992
Final Remedial Action Started 05/08/1998
Construction Completed 09/30/1999
Deleted from National Priorities List 02/26/2018
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment 06/26/2006

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 08/31/1987 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 12/29/1995 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 07/22/1998 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 12/08/1999 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 03/19/2001 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 08/09/1994 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/01/1987 02/26/1990 00
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - OU01 08/31/1987 09/30/1992 01
Record of Decision (EPA Performed) OU 01 - OU01 09/30/1992 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - OU01 11/10/1994 05/08/1998 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - OU01 05/08/1998 09/28/2000 01
Long-Term Response Action (PRP Performed, EPA Oversight) OU 01 - OU01 09/28/2000 10/04/2016 01

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.