Superfund Information Systems: Site Profile

Superfund Site:

RESIN DISPOSAL
JEFFERSON BOROUGH, PA

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 04/01/1982
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 10/26/1987
Remedy Selected 06/28/1991
Final Remedy Selected 09/29/1995
Remedial Action Started 06/05/1995
Final Remedial Action Started 10/09/2014
Construction Completed 11/20/1996
Deleted from National Priorities List 10/21/2003
Most Recent Five-Year Review 12/29/2015
Site Ready for Reuse and Redevelopment 03/27/2018

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 06/24/1992 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 09/30/1996 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 06/10/1992 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/19/2000 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/21/2005 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 12/30/2010 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 12/29/2015 00
Five-Year Review OU 00 - SITEWIDE Estimated Dec 2020 - Feb 2021 00
Combined Remedial Investigation/Feasibility Study (State Oversight) OU 01 - SOIL 10/26/1987 06/28/1991 01
Record of Decision (EPA Performed) OU 01 - SOIL 06/28/1991 01
Explanation of Significant Differences (EPA Performed) OU 01 - SOIL 09/25/2018 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - SOIL 05/11/1992 12/21/1994* 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - SOIL 05/11/1992* 09/29/1995 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - SOIL 11/12/2013 03/24/2015 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - SOIL 06/05/1995 07/07/1995* 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - SOIL 09/29/1995* 04/25/1997 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - SOIL 10/09/2014 05/18/2017 01
Operation and Maintenance (PRP Performed, EPA Oversight) OU 01 - SOIL 03/30/2018 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 02 - GROUND WATER 06/24/1992 09/29/1995 02
Record of Decision (EPA Performed) OU 02 - GROUND WATER 09/29/1995 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.