Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 10/22/1990
Proposed to the National Priorities List 02/07/1992
Finalized on the National Priorities List 10/14/1992
Final Remedy Selected 05/07/1996
Remedial Action Started 02/14/2000
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 03/10/2016
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 01/31/2006 00
Five-Year Review OU 00 - SITEWIDE 03/10/2016 00
Five-Year Review OU 00 - SITEWIDE 05/03/2011 00
Combined Remedial Investigation/Feasibility Study OU 01 - RI/FS SOILS AND GROUNDWATER 09/02/1992 07/20/1995 01
Record of Decision OU 01 - RI/FS SOILS AND GROUNDWATER 05/07/1996 01
Remedial Design OU 01 - RI/FS SOILS AND GROUNDWATER 03/18/2003 05/08/2003 01
Remedial Design OU 01 - RI/FS SOILS AND GROUNDWATER 12/26/1996 02/14/2000 01
Remedial Action OU 01 - RI/FS SOILS AND GROUNDWATER 02/14/2000 03/07/2001 01
Remedial Action OU 01 - RI/FS SOILS AND GROUNDWATER 05/08/2003 04/06/2006 01
Combined Remedial Investigation/Feasibility Study OU 02 - OU02 11/06/1992 05/07/1996 02

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.