Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 11/01/1982
Proposed to the National Priorities List 09/08/1983
Finalized on the National Priorities List 09/21/1984
Remedial Investigation Started 01/12/1984
Remedy Selected 09/27/1990
Final Remedy Selected 02/02/2011
Remedial Action Started 09/27/1991
Final Remedial Action Started 09/21/2018
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 03/30/2016
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 10/26/1988 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 04/17/1992 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 07/09/2013 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 03/22/1991 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 05/17/1994 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 03/23/2001 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 04/04/2006 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 03/31/2011 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 03/30/2016 00
Five-Year Review OU 00 - SITEWIDE Estimated Mar - May 2021 00
Consent Decree (EPA Performed) OU 01 - CABOT 09/20/1996 01
Combined Remedial Investigation/Feasibility Study (State Performed) OU 01 - CABOT 01/12/1984 05/31/1987* 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - CABOT 11/17/1987* 09/27/1990 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - CABOT 05/17/1994 12/18/2012* 01
Record of Decision (EPA Performed) OU 01 - CABOT 09/27/1990 01
Record of Decision (EPA Performed) OU 01 - CABOT 02/02/2011 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - CABOT 04/12/1991 09/29/1993 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - CABOT 09/27/1991 09/23/1994 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - CABOT 09/27/1991 12/29/1993 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - CABOT 12/26/2013 09/21/2018 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - CABOT 12/29/1993 05/15/1997 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - CABOT 09/23/1994 05/15/1997 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - CABOT 03/20/2014 08/27/2015 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - CABOT 09/21/2018 Estimated Mar - May 2020 01
Remedial Investigation (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 07/19/2001 02/02/2011* 02
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 03/01/1995 04/23/2001 02
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 10/12/2005 02/02/2011 02
Proposed Plan (EPA Performed) OU 02 - KOPPERS SURFICIAL SOURCE 05/07/2001 05/07/2001 02
Remedial Design (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 04/12/1991 12/18/2012* 02
Remedial Action (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 09/27/1991 12/18/2012* 02
Remedial Action (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 09/29/1993 12/18/2012* 02
Remedial Action (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 07/15/2012* 10/18/2018 02
Remedial Action (PRP Performed, EPA Oversight) OU 02 - KOPPERS SURFICIAL SOURCE 09/09/2016 04/11/2019 02
Operation and Maintenance OU 02 - KOPPERS SURFICIAL SOURCE Estimated Jan - Mar 2015 02
Remedial Design (PRP Performed, EPA Oversight) OU 04 - FLORIDAN AQUIFER 09/23/2011 09/23/2011 04
Remedial Action (PRP Performed, EPA Oversight) OU 04 - FLORIDAN AQUIFER 09/23/2011 02/06/2012 04

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.