Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 12/01/1987
Preliminary Assessment/Site Investigation Completed 02/02/1999
Proposed to the National Priorities List 07/14/1989
Finalized on the National Priorities List 11/21/1989
Remedy Selected 08/14/1992
Final Remedy Selected 09/19/2001
Remedial Action Started 11/29/1993
Construction Completed 09/28/2011
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/26/2016
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 03/15/2001 00
Five-Year Review OU 00 - SITEWIDE 03/15/2006 00
Five-Year Review OU 00 - SITEWIDE 09/26/2016 00
Five-Year Review OU 00 - SITEWIDE 09/27/2011 00
Removal OU 01 - PSC 1,2,3,26 06/17/1996 03/13/1997 01
Combined Remedial Investigation/Feasibility Study OU 01 - PSC 1,2,3,26 07/23/1991 09/02/1997 01
Record of Decision OU 01 - PSC 1,2,3,26 09/02/1997 01
Record of Decision OU 01 - PSC 1,2,3,26 10/11/1994 01
Remedial Design OU 01 - PSC 1,2,3,26 08/22/1994 12/29/1994 01
Remedial Action OU 01 - PSC 1,2,3,26 12/30/1994 10/23/2000 01
Combined Remedial Investigation/Feasibility Study OU 02 - PSC 11 07/23/1991 09/27/1996 02
Record of Decision OU 02 - PSC 11 09/27/1996 02
Combined Remedial Investigation/Feasibility Study OU 03 - PSC 16 & 17 02/14/1992 08/14/1992 03
Record of Decision OU 03 - PSC 16 & 17 08/14/1992 03
Record of Decision OU 03 - PSC 16 & 17 09/02/1997 03
Remedial Design OU 03 - PSC 16 & 17 10/01/2018 11/14/2018 03
Remedial Design OU 03 - PSC 16 & 17 10/12/1992 12/21/1993 03
Remedial Action OU 03 - PSC 16 & 17 11/29/1993 02/10/1997 03
Removal OU 04 - PSC 6,10,12,13,22 08/10/1995 06/16/1998 04
Combined Remedial Investigation/Feasibility Study OU 04 - PSC 6,10,12,13,22 09/15/1992 04/02/1999 04
Record of Decision OU 04 - PSC 6,10,12,13,22 04/02/1999 04
Combined Remedial Investigation/Feasibility Study OU 05 - PSC 8 & 14 06/20/1993 02/11/1998 05
Record of Decision OU 05 - PSC 8 & 14 02/11/1998 05
Record of Decision OU 05 - PSC 8 & 14 06/23/1995 05
Remedial Design OU 05 - PSC 8 & 14 10/15/1995 11/17/1995 05
Remedial Action OU 05 - PSC 8 & 14 01/16/1996 12/24/1996 05
Combined Remedial Investigation/Feasibility Study OU 06 - GROUND WATER 04/03/1998 09/19/2001 06
Record of Decision OU 06 - GROUND WATER 09/19/2001 06
Remedial Design OU 06 - GROUND WATER 04/15/2013 06
Remedial Design OU 06 - GROUND WATER 04/30/2003 02/05/2005 06
Remedial Design OU 06 - GROUND WATER 06/30/2003 12/03/2004 06
Remedial Design OU 06 - GROUND WATER 10/22/2001 06/07/2002 06
Remedial Action OU 06 - GROUND WATER 02/20/2006 09/07/2007 06
Remedial Action OU 06 - GROUND WATER 03/17/2014 09/17/2014 06
Remedial Action OU 06 - GROUND WATER 05/09/2006 06/13/2011 06
Remedial Action OU 06 - GROUND WATER 06/16/2005 08/19/2009 06
Remedial Action OU 06 - GROUND WATER 10/01/2005 08/19/2009 06
Remedial Action OU 06 - GROUND WATER 10/14/2008 01/15/2010 06
Remedial Action OU 06 - GROUND WATER 11/17/2005 09/07/2007 06
Removal OU 07 - PSC 9, 18, 24, & 30 04/03/1997 12/04/1997 07
Removal OU 07 - PSC 9, 18, 24, & 30 06/29/2000 03/19/2001 07
Removal OU 07 - PSC 9, 18, 24, & 30 09/21/1997 08/30/2000 07
Removal OU 07 - PSC 9, 18, 24, & 30 12/30/1996 12/03/1997 07

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.