Superfund Information Systems: Site Profile

Superfund Site:

CHARLES MACON LAGOON AND DRUM STORAGE
CORDOVA, NC

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 03/27/1985
Proposed to the National Priorities List 01/22/1987
Finalized on the National Priorities List 07/22/1987
Remedial Investigation Started 04/13/1988
Final Remedy Selected 09/30/1991
Remedial Action Started 06/28/1994
Final Remedial Action Started 06/28/1994
Construction Completed 11/06/1996
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 04/28/2015
Site Ready for Reuse and Redevelopment Estimated Aug - Oct 2020

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 04/13/1988 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 11/02/2000 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 12/05/1989 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 06/22/1992 00
Removal (EPA Performed) OU 00 - SITEWIDE 11/23/1983 01/17/1984 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/26/2000 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/28/2005 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 05/11/2010 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 04/28/2015 00
Five-Year Review OU 00 - SITEWIDE Estimated Apr - Jun 2020 00
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - OU01 04/13/1988 09/30/1991 01
Record of Decision (EPA Performed) OU 01 - OU01 09/30/1991 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - OU01 10/09/1992 06/28/1994 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - OU01 06/28/1994 03/06/2007 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - OU01 06/28/1994 09/28/2006 01
Long-Term Response Action (PRP Performed, EPA Oversight) OU 01 - OU01 02/22/1996 Estimated Dec 2020 - Feb 2021 01

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.