Superfund Information Systems: Site Profile

Superfund Site:

BURLINGTON INDUSTRIES CHERAW
CHERAW, SC

Cleanup Progress

Sign up for this Superfund site’s mailing list

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 09/13/2016
Proposed to the National Priorities List 01/18/2018
Finalized on the National Priorities List 05/17/2018
Remedial Investigation Started 06/20/2019
Remedy Selected Estimated Sep - Nov 2021
Remedial Action Started Not Yet Achieved
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 10/16/2017 00
Removal (EPA Performed) OU 00 - SITEWIDE 06/05/2017 03/14/2018 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 02/19/2018 Estimated Oct - Dec 2018 00
Combined Remedial Investigation/Feasibility Study OU 01 - OPERABLE UNIT 01 Estimated Sep - Nov 2019 Estimated Sep - Nov 2021 01
Record of Decision OU 01 - OPERABLE UNIT 01 Estimated Sep - Nov 2021 01
Administrative Order of Consent (EPA Performed) OU 02 - OPERABLE UNIT 02 06/20/2019 02
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 02 - OPERABLE UNIT 02 06/20/2019 Estimated Sep - Nov 2021 02
Record of Decision OU 02 - OPERABLE UNIT 02 Estimated Sep - Nov 2021 02

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.