ORLANDO GASIFICATION PLANT
ORLANDO, FL

Cleanup Progress

Sign up for this Superfund site’s mailing list

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 10/19/1989
Proposed to the National Priorities List Not Applicable
Finalized on the National Priorities List Not Applicable
Remedial Investigation Started 09/30/2003
Remedy Selected 09/25/2013
Remedial Action Started 09/25/2018
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Applicable
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 01/28/2002 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 09/30/2003 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 03/11/2004 00
Consent Decree (EPA Performed) OU 01 - OPERABLE UNIT 1 03/18/2015 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - OPERABLE UNIT 1 09/30/2003 09/25/2013 01
Record of Decision (EPA Performed) OU 01 - OPERABLE UNIT 1 09/25/2013 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - OPERABLE UNIT 1 11/25/2014 09/25/2018 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - OPERABLE UNIT 1 09/25/2018 Estimated Dec 2019 - Feb 2020 01
Operation and Maintenance OU 01 - OPERABLE UNIT 1 Estimated Dec 2020 - Feb 2021 01
Feasibility Study (PRP Performed, EPA Oversight) OU 02 - OPERABLE UNIT 2 01/01/2009 02
Proposed Plan OU 02 - OPERABLE UNIT 2 Estimated Oct - Dec 2020 Estimated May - Jul 2021 02
Operation and Maintenance OU 02 - OPERABLE UNIT 2 Estimated May - Jul 2019 02

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.