Site Milestones

Milestone Date(s)
Initial Assessment Completed 09/14/1992
Proposed to the National Priorities List 04/23/1999
Finalized on the National Priorities List 07/22/1999
Remedial Investigation Started Not Yet Achieved
Final Remedy Selected 09/24/1997
Remedial Action Started 09/29/2000
Final Remedial Action Started 09/29/2000
Construction Completed 06/21/2004
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/17/2014
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 06/18/2010 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 09/09/2009 00
Removal (EPA Performed) OU 00 - SITEWIDE 03/01/1991 05/30/1992 00
Removal (EPA Performed) OU 00 - SITEWIDE 04/19/1992 04/10/1996 00
Removal (EPA Performed) OU 00 - SITEWIDE 04/10/1996 04/10/1996 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/09/2009 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/17/2014 00
Five-Year Review OU 00 - SITEWIDE Estimated Sep - Nov 2019 00
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - OU01 08/07/1995* 09/24/1997 01
Record of Decision (EPA Performed) OU 01 - OU01 09/24/1997 01
Explanation of Significant Differences (EPA Performed) OU 01 - OU01 08/24/2000 01
Explanation of Significant Differences (EPA Performed) OU 01 - OU01 08/17/2010 01
Remedial Design (EPA Performed) OU 01 - OU01 09/05/1997 05/04/2000 01
Remedial Design (EPA Performed) OU 01 - OU01 12/30/1999 06/01/2000 01
Remedial Action (EPA Performed) OU 01 - OU01 09/29/2000 06/21/2002 01
Remedial Action (EPA Performed) OU 01 - OU01 09/29/2000 12/17/2004 01

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.

Top of Page