YEOMAN CREEK LANDFILL
WAUKEGAN, IL

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 02/01/1984
Proposed to the National Priorities List 06/24/1988
Finalized on the National Priorities List 03/31/1989
Remedial Investigation Started 12/22/1989
Final Remedy Selected 09/30/1996
Final Remedial Action Started 10/04/2001
Construction Completed 09/23/2005
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 08/24/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 12/22/1989 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 02/05/1999 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 04/07/1999 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 06/08/1999 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 04/10/2007 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 04/28/1998 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 06/23/1998 04/13/2000 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 02/27/2007 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 02/24/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 08/24/2017 00
Five-Year Review OU 00 - SITEWIDE Estimated Aug - Oct 2022 00
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - INITIAL RI/FS 12/22/1989 09/30/1996 01
Record of Decision (EPA Performed) OU 01 - INITIAL RI/FS 09/30/1996 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - INITIAL RI/FS 02/04/1999 10/04/2001 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - INITIAL RI/FS 10/04/2001 01
Removal (PRP Performed, EPA Oversight) OU 02 - FENCE 09/15/1990 12/30/1994 02
Removal (PRP Performed, EPA Oversight) OU 03 - LANDFILL GAS 11/16/1992 06/19/1995 03

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.