Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 06/24/1988
Proposed to the National Priorities List 06/24/1988
Finalized on the National Priorities List 03/31/1989
Remedy Selected 08/16/1996
Final Remedy Selected 09/26/2003
Remedial Action Started 06/23/1997
Remedy Construction Completed 08/01/2013
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 08/22/2017
Site Ready for Reuse and Redevelopment 08/28/2014

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 02/28/1990 10/01/1993 00
Removal OU 00 - SITEWIDE 05/04/1998 09/22/1999 00
Five-Year Review OU 00 - SITEWIDE 08/22/2017 00
Five-Year Review OU 00 - SITEWIDE 08/30/2012 00
Five-Year Review OU 00 - SITEWIDE 09/04/2002 00
Five-Year Review OU 00 - SITEWIDE 09/04/2007 00
Combined Remedial Investigation/Feasibility Study OU 01 - GROUNDWATER 05/25/1990 09/30/1998 01
Record of Decision OU 01 - GROUNDWATER 09/30/1998 01
Record of Decision Amendment OU 01 - GROUNDWATER 09/26/2003 01
Remedial Design OU 01 - GROUNDWATER 01/02/2001 05/21/2004 01
Remedial Action OU 01 - GROUNDWATER 04/30/2009 06/08/2015 01
Long-Term Response Action OU 01 - GROUNDWATER 10/31/2013 01
Combined Remedial Investigation/Feasibility Study OU 02 - LAGOON AREA 08/26/1991 09/30/1998 02
Record of Decision OU 02 - LAGOON AREA 09/30/1998 02
Remedial Design OU 02 - LAGOON AREA 01/02/2001 09/25/2002 02
Remedial Design OU 02 - LAGOON AREA 09/29/2005 02
Remedial Action OU 02 - LAGOON AREA 09/29/2005 09/13/2012 02
Combined Remedial Investigation/Feasibility Study OU 03 - CREEKS (WILDCAT & KOKOMO) 03/27/1992 09/30/1998 03
Remedial Design OU 03 - CREEKS (WILDCAT & KOKOMO) 01/02/2001 05/21/2004 03
Remedial Action OU 03 - CREEKS (WILDCAT & KOKOMO) 04/30/2007 10/05/2010 03
Combined Remedial Investigation/Feasibility Study OU 04 - MARKLAND AVE QUARRY 03/27/1992 09/30/1998 04
Remedial Design OU 04 - MARKLAND AVE QUARRY 01/02/2001 02/04/2004 04
Remedial Action OU 04 - MARKLAND AVE QUARRY 07/31/2009 05/09/2011 04
Combined Remedial Investigation/Feasibility Study OU 05 - MAIN PLANT 03/27/1992 09/30/1998 05
Combined Remedial Investigation/Feasibility Study OU 05 - MAIN PLANT 07/01/1997 09/30/1998 05
Combined Remedial Investigation/Feasibility Study OU 05 - MAIN PLANT 08/23/1995 08/16/1996 05
Record of Decision OU 05 - MAIN PLANT 08/16/1996 05
Record of Decision OU 05 - MAIN PLANT 09/30/1998 05
Remedial Design OU 05 - MAIN PLANT 01/02/2001 09/30/2003 05
Remedial Design OU 05 - MAIN PLANT 09/03/1996 06/23/1997 05
Remedial Action OU 05 - MAIN PLANT 06/23/1997 05
Remedial Action OU 05 - MAIN PLANT 12/20/2001 08/09/2011 05
Combined Remedial Investigation/Feasibility Study OU 06 - SLAG AREA/CHAFFIN QUARRY 03/27/1992 09/30/1998 06
Remedial Design OU 06 - SLAG AREA/CHAFFIN QUARRY 01/02/2001 07/01/2004 06
Remedial Action OU 06 - SLAG AREA/CHAFFIN QUARRY 04/30/2009 08/10/2011 06

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.