Superfund Information Systems: Site Profile

Superfund Site:

VELSICOL CHEMICAL CORP. (MICHIGAN)
ST. LOUIS, MI

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 05/01/1982
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 02/14/1997
Remedy Selected 02/12/1999
Remedial Action Started 01/27/1983
Construction Completed 09/25/1992
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/19/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Consent Decree (EPA Performed) OU 00 - SITEWIDE 12/27/1982 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 05/29/2008 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 06/18/1998 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 08/27/1997 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/25/2002 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/24/2007 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/21/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/19/2017 00
Combined Remedial Investigation/Feasibility Study (State Performed) OU 01 - MAIN PLANT SITE 01/01/2002 11/01/2011 01
Record of Decision (EPA Performed) OU 01 - MAIN PLANT SITE 06/22/2012 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - MAIN PLANT SITE 12/27/1982 01/27/1983 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 06/28/2012 04/02/2015 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 06/28/2012 Estimated Dec 2019 - Feb 2020 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 08/14/2013 02/08/2017 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 08/14/2013 06/27/2018 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 08/14/2013 07/14/2014 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 08/14/2013 09/30/2015 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 08/14/2013 01
Remedial Design (EPA Performed) OU 01 - MAIN PLANT SITE 03/29/2018 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - MAIN PLANT SITE 01/27/1983 12/01/1984 01
Remedial Action (EPA Performed) OU 01 - MAIN PLANT SITE 11/27/2012 09/26/2016 01
Remedial Action (EPA Performed) OU 01 - MAIN PLANT SITE 05/06/2014 Estimated Sep - Nov 2020 01
Remedial Action (EPA Performed) OU 01 - MAIN PLANT SITE 08/02/2014 03/27/2015 01
Remedial Action (EPA Performed) OU 01 - MAIN PLANT SITE 07/20/2017 03/28/2019 01
Remedial Action (EPA Performed) OU 01 - MAIN PLANT SITE 08/31/2018 01
Remedial Action OU 01 - MAIN PLANT SITE Estimated Sep - Nov 2021 01
Long-Term Response Action (EPA Performed) OU 01 - MAIN PLANT SITE 10/01/2012 01
Operation and Maintenance (PRP Performed, EPA Oversight) OU 01 - MAIN PLANT SITE 02/12/1990 09/23/1993 01
Removal (EPA Performed) OU 02 - PINE RIVER 08/03/1998 10/20/1999 02
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 02 - PINE RIVER 02/14/1997 02/12/1999 02
Record of Decision (EPA Performed) OU 02 - PINE RIVER 02/12/1999 02
Remedial Design (EPA Performed) OU 02 - PINE RIVER 03/24/1999 09/29/2003 02
Remedial Action (EPA Performed) OU 02 - PINE RIVER 05/21/1999 09/06/2011 02
Removal (EPA Performed) OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM 05/18/2015 04/25/2016* 03
Removal (EPA Performed) OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM 11/20/2016* 05/18/2017 03
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM 05/03/2013 Estimated Mar - May 2020 03
Record of Decision OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM Estimated Mar - May 2020 03
Remedial Design OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM Estimated Mar - May 2021 03
Remedial Action OU 03 - ATHLETIC FIELD REMOVAL ACTION / DOWNSTREAM Estimated Mar - May 2020 Estimated Jun - Aug 2021 03
Combined Remedial Investigation/Feasibility Study OU 04 - PINE RIVER DOWNSTREAM Estimated Sep - Nov 2019 04

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.