Superfund Information Systems: Site Profile

Superfund Site:

ELECTROVOICE
BUCHANAN, MI

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 09/01/1982
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/21/1984
Remedial Investigation Started 09/04/1987
Remedy Selected 06/23/1992
Final Remedy Selected 09/21/1999
Remedial Action Started 05/24/1996
Final Remedial Action Started 05/24/1996
Construction Completed 09/21/1999
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 06/30/2016
Site Ready for Reuse and Redevelopment 01/29/2008

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 10/08/1987 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 12/21/1993 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 03/04/1996 00
Five-Year Review (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/28/2001 00
Five-Year Review (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/22/2006 00
Five-Year Review (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 09/20/2011 00
Five-Year Review (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 06/30/2016 00
Five-Year Review OU 00 - SITEWIDE Estimated Jun - Aug 2021 00
Combined Remedial Investigation/Feasibility Study (State Performed) OU 01 - ONSITE GW, LAGOON CAP & SOILS 09/04/1987 10/08/1987* 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 10/08/1987* 06/24/1992 01
Record of Decision (EPA Performed) OU 01 - ONSITE GW, LAGOON CAP & SOILS 06/23/1992 01
Explanation of Significant Differences (EPA Performed) OU 01 - ONSITE GW, LAGOON CAP & SOILS 06/02/1993 01
Explanation of Significant Differences (EPA Performed) OU 01 - ONSITE GW, LAGOON CAP & SOILS 05/04/1995 01
Explanation of Significant Differences (EPA Performed) OU 01 - ONSITE GW, LAGOON CAP & SOILS 05/23/1996 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 09/29/1993 11/08/1995 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 05/08/1995 05/24/1996 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 05/24/1996 03/17/1997 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 05/24/1996 11/26/2003 01
Operation and Maintenance (PRP Performed, EPA Oversight) OU 01 - ONSITE GW, LAGOON CAP & SOILS 03/17/1997 01
Consent Decree (EPA Performed) OU 02 - OFFSITE GROUNDWATER 02/15/2001 02
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 02 - OFFSITE GROUNDWATER 09/15/1992 09/21/1999 02
Record of Decision (EPA Performed) OU 02 - OFFSITE GROUNDWATER 09/21/1999 02
Remedial Design (PRP Performed, EPA Oversight) OU 02 - OFFSITE GROUNDWATER 04/12/2001 09/19/2003 02
Long-Term Response Action (PRP Performed, EPA Oversight) OU 02 - OFFSITE GROUNDWATER 09/19/2003 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.