Superfund Information Systems: Site Profile

Superfund Site:

ALLIED PAPER, INC./PORTAGE CREEK/KALAMAZOO RIVER
KALAMAZOO, MI

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 11/08/1985
Proposed to the National Priorities List 05/05/1989
Finalized on the National Priorities List 08/30/1990
Remedial Investigation Started 12/28/1990
Remedy Selected 02/10/1998
Remedial Action Started 09/27/2002
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 10/17/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 01/23/1998 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 11/16/2006 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 02/15/2005 00
Removal (EPA Performed) OU 00 - SITEWIDE 08/03/1998 10/22/1999 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 08/03/1998 10/22/1999 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 11/27/2006 01/16/2008 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 10/18/2007 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 10/18/2012 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 10/17/2017 00
Administrative Order of Consent (EPA Performed) OU 01 - ALLIED PAPER/BRYANT MILL POND 11/01/1990 01
Removal (PRP Performed, EPA Oversight) OU 01 - ALLIED PAPER/BRYANT MILL POND 11/01/1990 07/17/1991 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - ALLIED PAPER/BRYANT MILL POND 12/28/1990 03/07/2008* 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - ALLIED PAPER/BRYANT MILL POND 03/07/2008* 09/21/2016 01
Record of Decision (EPA Performed) OU 01 - ALLIED PAPER/BRYANT MILL POND 09/21/2016 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - ALLIED PAPER/BRYANT MILL POND 02/28/2017 Estimated Jun - Aug 2020 01
Remedial Action OU 01 - ALLIED PAPER/BRYANT MILL POND Estimated Jun - Aug 2020 01
Consent Decree (EPA Performed) OU 02 - WILLOW BLVD/A-SITE 09/30/2009 02
Combined Remedial Investigation/Feasibility Study (State Oversight) OU 02 - WILLOW BLVD/A-SITE 12/28/1990 09/27/2006 02
Record of Decision (EPA Performed) OU 02 - WILLOW BLVD/A-SITE 09/27/2006 02
Remedial Design (PRP Performed, EPA Oversight) OU 02 - WILLOW BLVD/A-SITE 04/21/2009 04/27/2011 02
Remedial Action (PRP Performed, EPA Oversight) OU 02 - WILLOW BLVD/A-SITE 04/27/2011 09/25/2014 02
Operation and Maintenance (PRP Performed, EPA Oversight) OU 02 - WILLOW BLVD/A-SITE 03/16/2015 02
Combined Remedial Investigation/Feasibility Study (State Oversight) OU 03 - KING HIGHWAY LANDFILL 12/28/1990 02/10/1998 03
Record of Decision (EPA Performed) OU 03 - KING HIGHWAY LANDFILL 02/10/1998 03
Remedial Design (State Oversight) OU 03 - KING HIGHWAY LANDFILL 06/30/1999 09/27/2002 03
Remedial Action (State Oversight) OU 03 - KING HIGHWAY LANDFILL 09/27/2002 06/26/2013 03
Consent Decree (EPA Performed) OU 04 - 12TH STREET LANDFILL 05/18/2005 04
Combined Remedial Investigation/Feasibility Study (State Oversight) OU 04 - 12TH STREET LANDFILL 12/28/1990 09/28/2001 04
Record of Decision (EPA Performed) OU 04 - 12TH STREET LANDFILL 09/28/2001 04
Remedial Design (PRP Performed, EPA Oversight) OU 04 - 12TH STREET LANDFILL 02/15/2005 03/25/2010 04
Remedial Action (PRP Performed, EPA Oversight) OU 04 - 12TH STREET LANDFILL 03/25/2010 10/01/2012 04
Long-Term Response Action OU 04 - 12TH STREET LANDFILL Estimated Aug - Oct 2020 04
Administrative Order of Consent (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 02/21/2007 05
Administrative Order of Consent (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 06/08/2009 05
Unilateral Administrative Order (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 04/14/2016 05
Unilateral Administrative Order (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 12/16/2016 05
Removal (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 03/19/2007 03/30/2010 05
Removal (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 09/26/2011 07/11/2014 05
Removal OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Jun - Aug 2015 Estimated Oct - Dec 2017 05
Removal (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 08/01/2016 Estimated Aug - Oct 2019 05
Feasibility Study (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 08/02/2002 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 12/28/1990 10/30/2000 05
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 08/02/2002 07/10/2003 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 02/21/2007 09/28/2015 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 12/01/2010 09/28/2017 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 05/10/2012 Estimated Dec 2019 - Feb 2020 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 06/17/2013 Estimated Sep - Nov 2021 05
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 03/15/2017 05
Record of Decision (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 09/28/2015 05
Record of Decision (EPA Performed) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 09/28/2017 05
Record of Decision OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Dec 2019 - Feb 2020 05
Record of Decision OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Sep - Nov 2021 05
Remedial Design (PRP Performed, EPA Oversight) OU 05 - KALAMAZOO RIVER/PORTAGE CREEK 03/23/2017 Estimated Apr - Jun 2020 05
Remedial Design OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Jun - Aug 2020 05
Remedial Design OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Sep - Nov 2020 Estimated Sep - Nov 2021 05
Remedial Action OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Apr - Jun 2020 05
Remedial Action OU 05 - KALAMAZOO RIVER/PORTAGE CREEK Estimated Sep - Nov 2021 05
Removal (PRP Performed, EPA Oversight) OU 07 - PLAINWELL MILL 08/05/2009 03/01/2011 07
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 07 - PLAINWELL MILL 02/15/2005 09/23/2015 07
Proposed Plan (EPA Performed) OU 07 - PLAINWELL MILL 10/28/2014 Estimated Jun - Aug 2015 07
Record of Decision (EPA Performed) OU 07 - PLAINWELL MILL 09/23/2015 07
Remedial Design (PRP Performed, EPA Oversight) OU 07 - PLAINWELL MILL 01/05/2016 04/26/2018 07
Remedial Action (PRP Performed, EPA Oversight) OU 07 - PLAINWELL MILL 04/26/2018 Estimated Dec 2019 - Feb 2020 07

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.