Superfund Information Systems: Site Profile

Superfund Site:

TITTABAWASSEE RIVER, SAGINAW RIVER & BAY
MIDLAND, MI

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 07/01/1984
Proposed to the National Priorities List Not Applicable
Finalized on the National Priorities List Not Applicable
Remedial Investigation Started 01/14/2010
Remedy Selected Not Yet Achieved
Remedial Action Started Not Yet Achieved
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Applicable
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 01/14/2010 00
Administrative Order of Consent (EPA Performed) OU 01 - REACH D 07/12/2007 01
Removal (PRP Performed, EPA Oversight) OU 01 - REACH D 07/09/2007 10/15/2008 01
Administrative Order of Consent (EPA Performed) OU 02 - REACH J/K 07/12/2007 02
Removal (PRP Performed, EPA Oversight) OU 02 - REACH J/K 08/06/2007 05/02/2008 02
Administrative Order of Consent (EPA Performed) OU 03 - REACH O 07/12/2007 03
Removal (PRP Performed, EPA Oversight) OU 03 - REACH O 08/13/2007 04/10/2008 03
Administrative Order of Consent (EPA Performed) OU 04 - WICKESPARK 11/15/2007 04
Removal (PRP Performed, EPA Oversight) OU 04 - WICKESPARK 11/27/2007 08/04/2008 04
Administrative Order of Consent (EPA Performed) OU 05 - RIVERSIDE BOULEVARD AREA 07/15/2008 05
Removal (PRP Performed, EPA Oversight) OU 05 - RIVERSIDE BOULEVARD AREA 08/13/2008 02/01/2010 05
Administrative Order of Consent (EPA Performed) OU 06 - EXPOSURE UNIT-002 02/27/2009 06
Removal (PRP Performed, EPA Oversight) OU 06 - EXPOSURE UNIT-002 03/24/2009 09/11/2012 06
Administrative Order of Consent (EPA Performed) OU 07 - TASK 1 EXPOSURE CONTROLS 05/26/2011 07
Removal (PRP Performed, EPA Oversight) OU 07 - TASK 1 EXPOSURE CONTROLS 07/10/2011 07
Administrative Order of Consent (EPA Performed) OU 08 - ISLAND MM 07/08/2011 08
Removal (PRP Performed, EPA Oversight) OU 08 - ISLAND MM 07/08/2011 07/12/2012 08
Administrative Order of Consent (EPA Performed) OU 09 - SEGMENT 1 11/01/2011 09
Removal (PRP Performed, EPA Oversight) OU 09 - SEGMENT 1 05/29/2012 09/27/2017 09
Administrative Order of Consent (EPA Performed) OU 10 - SEGMENT 2 11/21/2013 10
Removal (PRP Performed, EPA Oversight) OU 10 - SEGMENT 2 11/21/2013 Estimated Aug - Oct 2019 10
Administrative Order of Consent (EPA Performed) OU 11 - TR-FLOODPLAIN 01/08/2015 11
Removal (PRP Performed, EPA Oversight) OU 11 - TR-FLOODPLAIN 01/08/2015 Estimated Jul - Sep 2021 11
Administrative Order of Consent (EPA Performed) OU 12 - SEGMENT 3 02/25/2016 12
Removal (PRP Performed, EPA Oversight) OU 12 - SEGMENT 3 05/09/2016 Estimated Oct - Dec 2019 12
Administrative Order of Consent (EPA Performed) OU 13 - SEGMENTS 4 & 5 02/08/2017 13
Removal OU 13 - SEGMENTS 4 & 5 Estimated Jun - Aug 2017 13
Administrative Order of Consent (EPA Performed) OU 14 - SEGMENTS 6 & 7 05/21/2019 14
Removal OU 14 - SEGMENTS 6 & 7 Estimated Aug - Oct 2019 14
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 15 - T RIVER 01/14/2010 15

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.