Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed Not Yet Achieved
Proposed to the National Priorities List Not Applicable
Finalized on the National Priorities List Not Applicable
Remedy Selected 09/30/2016
Remedial Action Started Not Yet Achieved
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Applicable
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 03/21/2001 06/01/2001 00
Removal OU 00 - SITEWIDE 05/10/2002 00
Removal OU 00 - SITEWIDE 03/01/2006 00
Combined Remedial Investigation/Feasibility Study OU 01 - SEMS 04/05/2004 09/30/2016 01
Record of Decision OU 01 - SEMS 09/30/2016 01
Removal OU 02 - ARSENIC SITE REMOVAL 06/06/2016 02

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.