Superfund Information Systems: Site Profile

Superfund Site:

TOWN OF PINES GROUNDWATER PLUME
TOWN OF PINES, IN

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 08/28/2001
Proposed to the National Priorities List Not Applicable
Finalized on the National Priorities List Not Applicable
Remedial Investigation Started 04/05/2004
Remedy Selected 09/30/2016
Remedial Action Started Not Yet Achieved
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Applicable
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 01/24/2003 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 04/05/2004 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 03/17/2016 00
Removal (EPA Performed) OU 00 - SITEWIDE 03/21/2001 06/01/2001 00
Removal (EPA Performed) OU 00 - SITEWIDE 05/10/2002 01/24/2003* 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 01/24/2003* 03/01/2006 00
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - SEMS 04/05/2004 09/30/2016 01
Proposed Plan (EPA Performed) OU 01 - SEMS 05/16/2016 07/15/2016 01
Record of Decision (EPA Performed) OU 01 - SEMS 09/30/2016 01
Explanation of Significant Differences (EPA Performed) OU 01 - SEMS 02/13/2020 01
Remedial Design OU 01 - SEMS Estimated May - Jul 2021 01
Removal (PRP Performed, EPA Oversight) OU 02 - ARSENIC SITE REMOVAL 06/06/2016 Estimated Dec 2020 - Feb 2021 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.