Site Milestones

Milestone Date(s)
Initial Assessment Completed 12/15/2004
Proposed to the National Priorities List 09/27/2006
Finalized on the National Priorities List 09/19/2007
Remedial Investigation Started 03/18/2005
Remedy Selected 09/05/2008
Remedial Action Started 05/26/2009
Final Remedial Action Started 11/02/2017
Construction Completed 09/27/2011
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 05/15/2019
Site Ready for Reuse and Redevelopment 06/28/2012

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Consent Decree (EPA Performed) OU 00 - SITEWIDE 03/21/2014 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 09/03/2004 00
Removal (EPA Performed) OU 00 - SITEWIDE 10/19/2004 10/09/2008 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 05/16/2014 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 05/15/2019 00
Partial NPL Deletion (EPA Performed) OU 00 - SITEWIDE 09/30/2019 00
Partial NPL Deletion OU 00 - SITEWIDE Estimated Sep - Nov 2021 00
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - SEMS 03/18/2005 09/05/2008 01
Record of Decision (EPA Performed) OU 01 - SEMS 09/05/2008 01
Remedial Design (EPA Performed) OU 01 - SEMS 07/01/2008 05/12/2009 01
Remedial Action (EPA Performed) OU 01 - SEMS 05/26/2009 09/12/2012 01
Remedial Action (EPA Performed) OU 01 - SEMS 01/11/2016 01/31/2017 01
Remedial Action (EPA Performed) OU 01 - SEMS 11/02/2017 Estimated Dec 2021 - Feb 2022 01
Long-Term Response Action (EPA Performed) OU 01 - SEMS 05/16/2014 01

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.