Milestone Date(s)
Initial Assessment Completed 07/01/1982
Proposed to the National Priorities List 06/23/1993
Finalized on the National Priorities List 02/23/1994
Remedial Investigation Started 03/31/1994
Remedy Selected 12/20/2001
Remedial Action Started 03/01/2005
Final Remedial Action Started 06/14/2017
Construction Completed 07/23/2007
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 07/08/2016
Site Ready for Reuse and Redevelopment 03/09/2020

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 03/31/1994 00
Consent Decree (EPA Performed) OU 00 - SITEWIDE 03/01/2005 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 08/17/1998 06/05/2001 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 06/28/2011 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 07/08/2016 00
Five-Year Review OU 00 - SITEWIDE Estimated Jun - Aug 2021 00
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - SITEWIDE -OU01 03/31/1994 12/20/2001 01
Record of Decision (EPA Performed) OU 01 - SITEWIDE -OU01 12/20/2001 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - SITEWIDE -OU01 10/19/2004 03/01/2005 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - SITEWIDE -OU01 03/01/2005 08/22/2007* 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - SITEWIDE -OU01 06/14/2017 01/16/2018 01
Long-Term Response Action (PRP Performed, EPA Oversight) OU 01 - SITEWIDE -OU01 08/22/2007 Estimated Aug - Oct 2022 01

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.

Top of Page