Superfund Information Systems: Site Profile

Superfund Site:

GULFCO MARINE MAINTENANCE
FREEPORT, TX

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 07/01/1980
Proposed to the National Priorities List 09/05/2002
Finalized on the National Priorities List 04/30/2003
Final Remedy Selected 09/29/2011
Remedial Action Started Not Yet Achieved
Remedy Construction Completed 09/29/2011
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/21/2016
Site Ready for Reuse and Redevelopment 08/24/2012

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 09/21/2016 00
Combined Remedial Investigation/Feasibility Study OU 01 - OU 01 (OU SPECIFIC) 07/29/2005 09/29/2011 01
Record of Decision OU 01 - OU 01 (OU SPECIFIC) 09/29/2011 01

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.