Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 09/01/1984
Proposed to the National Priorities List 10/15/1984
Finalized on the National Priorities List 06/10/1986
Remedy Selected 03/27/1987
Final Remedy Selected 09/22/2006
Remedial Action Started 01/25/1988
Construction Completed 09/30/2010
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 08/19/2016
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 05/12/1986 05/16/1986 00
Five-Year Review OU 00 - SITEWIDE 08/19/2016 00
Five-Year Review OU 00 - SITEWIDE 09/16/2011 00
Five-Year Review OU 00 - SITEWIDE 09/22/2006 00
Five-Year Review OU 00 - SITEWIDE 10/23/2000 00
Combined Remedial Investigation/Feasibility Study OU 01 - FRONTIER PARK ROAD 09/26/1984 03/27/1987 01
Record of Decision OU 01 - FRONTIER PARK ROAD 03/27/1987 01
Remedial Design OU 01 - FRONTIER PARK ROAD 06/05/1987 10/30/1987 01
Remedial Action OU 01 - FRONTIER PARK ROAD 01/25/1988 03/01/1989 01
Long-Term Response Action OU 01 - FRONTIER PARK ROAD 01/16/1996 01
Long-Term Response Action OU 01 - FRONTIER PARK ROAD 09/30/1988 01/16/1996 01
Operation and Maintenance OU 01 - FRONTIER PARK ROAD 01/21/2011 01/21/2011 01
Combined Remedial Investigation/Feasibility Study OU 02 - SITE 03/15/1991 09/06/1991 02
Combined Remedial Investigation/Feasibility Study OU 02 - SITE 09/26/1988 09/06/1991 02
Record of Decision OU 02 - SITE 09/06/1991 02
Record of Decision Amendment OU 02 - SITE 04/30/1998 02
Record of Decision Amendment OU 02 - SITE 09/22/2006 02
Remedial Design OU 02 - SITE 03/01/2010 07/15/2010 02
Remedial Design OU 02 - SITE 08/29/2001 05/17/2002 02
Remedial Design OU 02 - SITE 09/25/1992 05/22/1998 02
Remedial Action OU 02 - SITE 01/28/2011 02
Remedial Action OU 02 - SITE 03/30/2008 01/04/2010 02
Remedial Action OU 02 - SITE 05/10/2010 03/09/2011 02
Remedial Action OU 02 - SITE 05/22/1998 09/15/2011 02
Operation and Maintenance OU 02 - SITE 10/01/2008 02

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.