Superfund Information Systems: Site Profile

Superfund Site:

CENTRAL WOOD PRESERVING CO.
SLAUGHTER, LA

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 11/15/1994
Proposed to the National Priorities List 01/19/1999
Finalized on the National Priorities List 05/10/1999
Remedial Investigation Started 08/04/1998
Remedy Selected 04/05/2001
Final Remedial Action Started 07/21/2003
Construction Completed 09/08/2004
Deleted from National Priorities List 09/18/2009
Most Recent Five-Year Review 03/13/2019
Site Ready for Reuse and Redevelopment 09/24/2007

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Unilateral Administrative Order (EPA Performed) OU 00 - SITEWIDE 04/18/1995 00
Removal (EPA Performed) OU 00 - SITEWIDE 04/24/1995 09/18/1995 00
Operation and Maintenance (State Performed) OU 00 - SITEWIDE 09/15/2006 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 04/21/2009 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 04/09/2014 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 03/13/2019 00
Feasibility Study (EPA Performed) OU 01 - OU-01 12/10/1998 04/05/2001 01
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 01 - OU-01 08/04/1998 04/05/2001 01
Record of Decision (EPA Performed) OU 01 - OU-01 04/05/2001 01
Remedial Design (EPA Performed) OU 01 - OU-01 07/03/2001 06/21/2002 01
Remedial Action (EPA Performed) OU 01 - OU-01 07/21/2003 04/21/2005 01

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.