Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 09/04/2001
Proposed to the National Priorities List 09/13/2001
Finalized on the National Priorities List 09/05/2002
Final Remedy Selected 09/30/2008
Remedial Action Started 02/28/2012
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/28/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Five-Year Review OU 00 - SITEWIDE 09/28/2017 00
Combined Remedial Investigation/Feasibility Study OU 01 - SOURCE CONTROL 03/21/2002 09/30/2008 01
Record of Decision OU 01 - SOURCE CONTROL 09/30/2008 01
Remedial Design OU 01 - SOURCE CONTROL 03/01/2013 09/27/2013 01
Remedial Design OU 01 - SOURCE CONTROL 05/01/2013 01
Remedial Design OU 01 - SOURCE CONTROL 08/25/2011 03/09/2012 01
Remedial Design OU 01 - SOURCE CONTROL 09/14/2015 09/25/2017 01
Remedial Design OU 01 - SOURCE CONTROL 09/14/2015 01
Remedial Design OU 01 - SOURCE CONTROL 10/30/2009 03/09/2012 01
Remedial Action OU 01 - SOURCE CONTROL 02/28/2012 01
Remedial Action OU 01 - SOURCE CONTROL 07/15/2014 01

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.