Superfund Information Systems: Site Profile

Superfund Site:

ORONOGO-DUENWEG MINING BELT
JOPLIN, MO

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 06/25/1986
Proposed to the National Priorities List 06/24/1988
Finalized on the National Priorities List 08/30/1990
Remedial Investigation Started 04/24/1990
Remedy Selected 08/01/1996
Remedial Action Started 08/02/1996
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 08/25/2017
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 06/30/1994 00
Consent Decree (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 12/10/1996 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 12/16/1993 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 06/24/1994 00
Five-Year Review (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 09/27/2002 00
Five-Year Review (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 08/27/2007 00
Five-Year Review (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 08/29/2012 00
Five-Year Review (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 08/25/2017 00
Five-Year Review OU 00 - SITE EVALUATION/DISPOSITION Estimated Aug - Oct 2022 00
Administrative Order of Consent (EPA Performed) OU 01 - MINE AND MILL WASTE 08/02/1991 01
Administrative Order of Consent (EPA Performed) OU 01 - MINE AND MILL WASTE 03/08/2016 01
Consent Decree (EPA Performed) OU 01 - MINE AND MILL WASTE 03/06/1996 01
Consent Decree (EPA Performed) OU 01 - MINE AND MILL WASTE 03/26/2009 01
Consent Decree (EPA Performed) OU 01 - MINE AND MILL WASTE 09/28/2009 01
Consent Decree (EPA Performed) OU 01 - MINE AND MILL WASTE 09/13/2019 01
Unilateral Administrative Order (EPA Performed) OU 01 - MINE AND MILL WASTE 07/02/2008 01
Unilateral Administrative Order (EPA Performed) OU 01 - MINE AND MILL WASTE 11/25/2008 01
Unilateral Administrative Order (EPA Performed) OU 01 - MINE AND MILL WASTE 06/15/2016 01
Removal (EPA Performed) OU 01 - MINE AND MILL WASTE 08/26/2001 09/19/2008 01
Removal (EPA Performed) OU 01 - MINE AND MILL WASTE 12/10/2008 04/24/2009 01
Remedial Investigation (EPA Performed) OU 01 - MINE AND MILL WASTE 04/24/1990 02/13/2001 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - MINE AND MILL WASTE 08/02/1991 09/30/2004 01
Record of Decision (EPA Performed) OU 01 - MINE AND MILL WASTE 09/30/2004 01
Record of Decision Amendment (EPA Performed) OU 01 - MINE AND MILL WASTE 09/27/2013 01
Explanation of Significant Differences (EPA Performed) OU 01 - MINE AND MILL WASTE 05/05/2016 01
Remedial Design (EPA Performed) OU 01 - MINE AND MILL WASTE 02/07/2007 Estimated Sep - Nov 2020 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - MINE AND MILL WASTE 09/02/2008 06/12/2020 01
Remedial Design OU 01 - MINE AND MILL WASTE Estimated Sep - Nov 2021 Estimated Dec 2021 - Feb 2022 01
Remedial Design OU 01 - MINE AND MILL WASTE Estimated Sep - Nov 2021 Estimated Mar - May 2022 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - MINE AND MILL WASTE 02/07/2007 09/28/2017 01
Remedial Action (EPA Performed) OU 01 - MINE AND MILL WASTE 09/25/2007 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - MINE AND MILL WASTE 09/29/2017 03/09/2020 01
Remedial Action OU 01 - MINE AND MILL WASTE Estimated Mar - May 2022 01
Removal (EPA Performed) OU 02 - RESIDENTIAL YARDS 03/13/1995 03/12/1996 02
Feasibility Study (EPA Performed) OU 02 - RESIDENTIAL YARDS 09/15/1995* 08/01/1996 02
Record of Decision (EPA Performed) OU 02 - RESIDENTIAL YARDS 08/01/1996 02
Remedial Design (EPA Performed) OU 02 - RESIDENTIAL YARDS 08/03/1996 03/20/1998 02
Remedial Action (EPA Performed) OU 02 - RESIDENTIAL YARDS 08/02/1996 04/05/2002 02
Removal (EPA Performed) OU 03 - MINE WASTE YARD SOILS 03/11/2019 01/07/2020 03
Remedial Design (PRP Performed, EPA Oversight) OU 03 - MINE WASTE YARD SOILS 08/03/1996 03/20/1998 03
Remedial Action (EPA Performed) OU 03 - MINE WASTE YARD SOILS 04/01/1997 04/05/2002 03
Consent Decree (EPA Performed) OU 04 - GROUND WATER 01/19/2001 04
Consent Decree (EPA Performed) OU 04 - GROUND WATER 09/28/2009 04
Removal (PRP Performed, EPA Oversight) OU 04 - GROUND WATER 12/22/1993 09/30/2002 04
Removal (EPA Performed) OU 04 - GROUND WATER 11/08/1994 09/09/2005 04
Feasibility Study (PRP Performed, EPA Oversight) OU 04 - GROUND WATER 08/01/1995 07/29/1998 04
Record of Decision (EPA Performed) OU 04 - GROUND WATER 07/29/1998 04
Remedial Design (EPA Performed) OU 04 - GROUND WATER 02/15/2000 06/18/2001 04
Remedial Action (EPA Performed) OU 04 - GROUND WATER 06/18/2001 09/18/2007 04
Remedial Investigation (EPA Performed) OU 05 - SPRING RIVER BASIN 08/19/2005 Estimated Sep - Nov 2022 05
Feasibility Study (EPA Performed) OU 05 - SPRING RIVER BASIN 09/28/2018 05

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.