Superfund Information Systems: Site Profile

Superfund Site:

NEWTON COUNTY MINE TAILINGS
GRANBY, MO

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 07/23/1987
Proposed to the National Priorities List 04/30/2003
Finalized on the National Priorities List 09/29/2003
Remedial Investigation Started 09/29/2006
Remedy Selected 06/21/2010
Final Remedial Action Started 11/05/2014
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Consent Decree (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 07/07/2003 00
Unilateral Administrative Order (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION 07/09/1996 00
Five-Year Review (EPA Performed) OU 00 - SITE EVALUATION/DISPOSITION Estimated Nov 2019 - Jan 2020 00
Administrative Order of Consent (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 06/20/1997 01
Consent Decree (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 02/12/2007 01
Consent Decree (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 09/21/2010 01
Consent Decree (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 02/22/2012 01
Unilateral Administrative Order (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 04/15/2002 01
Removal (PRP Performed, EPA Oversight) OU 01 - DIAMOND/SPRING CITY/GRANBY 06/21/1996 08/18/2009 01
Removal (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 04/13/1998 08/18/2009* 01
Removal (PRP Performed, EPA Oversight) OU 01 - DIAMOND/SPRING CITY/GRANBY 07/07/1999 10/14/1999 01
Removal (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 04/01/2002 06/15/2002* 01
Removal (PRP Performed, EPA Oversight) OU 01 - DIAMOND/SPRING CITY/GRANBY 06/15/2002* 04/25/2003 01
Removal (PRP Performed, EPA Oversight) OU 01 - DIAMOND/SPRING CITY/GRANBY 12/01/2006 05/07/2013 01
Explanation of Significant Differences (EPA Performed) OU 01 - DIAMOND/SPRING CITY/GRANBY 09/26/2018 01
Removal (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 06/08/1998 04/17/2012 02
Removal (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 07/07/1999 10/14/1999 02
Removal (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 10/29/2001 03/23/2002 02
Removal (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 09/26/2003 04/17/2012 02
Removal (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 11/30/2018 Estimated Sep - Nov 2020 02
Removal OU 02 - REMAINDER OF NEWTON COUNTY Estimated Dec 2019 - Feb 2020 Estimated Dec 2020 - Feb 2021 02
Combined Remedial Investigation/Feasibility Study (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 09/29/2006 06/21/2010 02
Combined Remedial Investigation/Feasibility Study OU 02 - REMAINDER OF NEWTON COUNTY Estimated Jan - Mar 2020 Estimated Jul - Sep 2021 02
Record of Decision (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 06/21/2010 02
Record of Decision Amendment OU 02 - REMAINDER OF NEWTON COUNTY Estimated Sep - Nov 2021 02
Explanation of Significant Differences OU 02 - REMAINDER OF NEWTON COUNTY Estimated Jun - Aug 2020 02
Remedial Design (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 09/24/2010 08/10/2012 02
Remedial Design (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 08/01/2017 09/27/2018 02
Remedial Design (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 12/20/2018 02
Remedial Action (EPA Performed) OU 02 - REMAINDER OF NEWTON COUNTY 11/05/2014 02

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.