Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 12/01/1984
Proposed to the National Priorities List 10/15/1984
Finalized on the National Priorities List 07/22/1987
Remedy Selected 09/30/1991
Remedial Action Started 01/30/1992
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 12/31/2013
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 08/08/2002 00
Five-Year Review OU 00 - SITEWIDE 09/26/2003 00
Five-Year Review OU 00 - SITEWIDE 09/28/1998 00
Five-Year Review OU 00 - SITEWIDE 12/31/2008 00
Five-Year Review OU 00 - SITEWIDE 12/31/2013 00
Remedial Investigation OU 01 - LF 3&4,CP 1&2,FTA 1&2 02/14/1986 04/10/1991 01
Combined Remedial Investigation/Feasibility Study OU 01 - LF 3&4,CP 1&2,FTA 1&2 06/28/1991 09/29/1998 01
Record of Decision OU 01 - LF 3&4,CP 1&2,FTA 1&2 09/29/1998 01
Remedial Design OU 01 - LF 3&4,CP 1&2,FTA 1&2 12/16/1998 03/31/2000 01
Remedial Action OU 01 - LF 3&4,CP 1&2,FTA 1&2 02/05/2008 09/19/2014 01
Remedial Action OU 01 - LF 3&4,CP 1&2,FTA 1&2 09/07/1999 07/10/2000 01
Remedial Action OU 01 - LF 3&4,CP 1&2,FTA 1&2 09/07/1999 09/28/2001 01
Remedial Investigation OU 02 - CP-3 08/15/1987 04/10/1991 02
Feasibility Study OU 02 - CP-3 04/10/1991 09/30/1991 02
Combined Remedial Investigation/Feasibility Study OU 02 - CP-3 06/28/1991 09/30/1996 02
Record of Decision OU 02 - CP-3 09/30/1991 02
Record of Decision OU 02 - CP-3 09/30/1996 02
Remedial Design OU 02 - CP-3 05/26/2009 07/13/2009 02
Remedial Design OU 02 - CP-3 05/30/1995 09/30/1996 02
Remedial Design OU 02 - CP-3 09/30/1991 01/30/1992 02
Remedial Action OU 02 - CP-3 01/30/1992 09/30/1996 02
Remedial Action OU 02 - CP-3 09/14/2009 07/19/2010 02
Remedial Action OU 02 - CP-3 09/30/1996 07/10/2000 02
Remedial Investigation OU 03 - IWTP 02/24/1987 04/10/1991 03
Feasibility Study OU 03 - IWTP 03/30/1991 09/25/1992 03
Combined Remedial Investigation/Feasibility Study OU 03 - IWTP 07/25/1991 09/25/1992 03
Record of Decision OU 03 - IWTP 09/25/1992 03
Record of Decision OU 03 - IWTP 09/28/1995 03
Remedial Design OU 03 - IWTP 03/14/1996 04/08/1997 03
Remedial Design OU 03 - IWTP 09/30/1992 07/12/1993 03
Remedial Action OU 03 - IWTP 08/10/1993 09/28/1994 03
Remedial Action OU 03 - IWTP 12/23/1996 09/29/1999 03
Remedial Investigation OU 04 - LF 1&2 11/13/1987 04/10/1991 04
Combined Remedial Investigation/Feasibility Study OU 04 - LF 1&2 04/10/1991 06/14/1994 04
Record of Decision OU 04 - LF 1&2 06/14/1994 04
Record of Decision Amendment OU 04 - LF 1&2 09/25/2017 04
Remedial Design OU 04 - LF 1&2 06/14/1994 03/20/1996 04
Remedial Design OU 04 - LF 1&2 06/14/1994 04/03/1995 04
Remedial Design OU 04 - LF 1&2 10/01/1998 08/30/1999 04
Remedial Design OU 04 - LF 1&2 10/06/2016 09/25/2017 04
Remedial Action OU 04 - LF 1&2 07/17/1997 09/17/1997 04
Remedial Action OU 04 - LF 1&2 09/14/1995 04/23/1998 04
Remedial Action OU 04 - LF 1&2 09/25/2017 04
Removal OU 05 - TOOELE RAIL SHOP 09/24/2002 09/30/2004 05
Remedial Investigation OU 05 - TOOELE RAIL SHOP 03/23/1989 04/10/1991 05
Remedial Investigation OU 05 - TOOELE RAIL SHOP 05/31/1999 01/30/2004 05
Feasibility Study OU 05 - TOOELE RAIL SHOP 06/19/2003 05/30/2004 05
Combined Remedial Investigation/Feasibility Study OU 05 - TOOELE RAIL SHOP 08/13/1991 05/31/1999 05
Record of Decision OU 05 - TOOELE RAIL SHOP 09/12/2006 05
Remedial Design OU 05 - TOOELE RAIL SHOP 01/25/2007 05/16/2007 05
Remedial Action OU 05 - TOOELE RAIL SHOP 11/17/2006 09/28/2007 05
Combined Remedial Investigation/Feasibility Study OU 06 - OU6 09/10/1992 09/30/1997 06
Record of Decision OU 06 - OU6 09/30/1997 06
Remedial Design OU 06 - OU6 02/19/2014 02/19/2014 06
Remedial Design OU 06 - OU6 06/19/1997 07/13/1998 06
Remedial Action OU 06 - OU6 03/30/1999 03/23/2000 06
Remedial Action OU 06 - OU6 07/20/2014 10/01/2015 06
Combined Remedial Investigation/Feasibility Study OU 07 - OU7 05/15/1992 09/28/1995 07
Record of Decision OU 07 - OU7 09/28/1995 07
Remedial Design OU 07 - OU7 03/18/1996 07/30/1996 07
Remedial Action OU 07 - OU7 11/05/1996 09/30/1998 07
Remedial Investigation OU 08 - OU8 05/03/1995 03/15/2002 08
Feasibility Study OU 08 - OU8 03/11/2002 03/06/2003 08
Combined Remedial Investigation/Feasibility Study OU 08 - OU8 05/03/1995 09/30/1997 08
Record of Decision OU 08 - OU8 08/05/2005 08
Record of Decision OU 08 - OU8 09/30/1997 08
Remedial Design OU 08 - OU8 03/31/2004 07/27/2004 08
Remedial Design OU 08 - OU8 05/23/1997 10/09/1997 08
Remedial Action OU 08 - OU8 05/01/2005 12/30/2005 08
Remedial Action OU 08 - OU8 10/20/1997 09/30/1998 08
Removal OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 01/06/2016 07/31/2017 09
Removal OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 08/25/2003 09/30/2004 09
Removal OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 10/06/2003 09/30/2004 09
Remedial Investigation OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 05/31/1999 05/05/2005 09
Feasibility Study OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 10/29/2004 08/10/2005 09
Record of Decision OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 09/23/2015 09
Remedial Design OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 03/31/2015 09/30/2015 09
Remedial Design OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 04/27/2015 09/30/2015 09
Remedial Design OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 12/18/2014 09/30/2015 09
Remedial Action OU 09 - 800 AREA, 1100 AREA, GOLF COURSE, PONDS 09/30/2015 09/22/2016 09
Remedial Investigation OU 10 - WEST GATE AREA PLUMES 06/19/2001 12/14/2009 10
Feasibility Study OU 10 - WEST GATE AREA PLUMES 09/04/2008 09/23/2015 10
Record of Decision OU 10 - WEST GATE AREA PLUMES 09/23/2015 10
Remedial Design OU 10 - WEST GATE AREA PLUMES 02/27/2015 09/30/2015 10
Remedial Action OU 10 - WEST GATE AREA PLUMES 09/30/2015 09/22/2016 10
Remedial Investigation OU 11 - BASE GAS STATION 06/19/2001 05/05/2005 11
Feasibility Study OU 11 - BASE GAS STATION 09/04/2008 07/21/2015 11
Record of Decision OU 11 - BASE GAS STATION 07/21/2015 11
Remedial Design OU 11 - BASE GAS STATION 12/18/2014 09/30/2015 11
Remedial Action OU 11 - BASE GAS STATION 09/30/2015 09/21/2017 11
Removal OU 12 - ROY PLUME 11/08/2004 04/05/2006 12
Remedial Investigation OU 12 - ROY PLUME 05/31/1999 04/28/2005 12
Feasibility Study OU 12 - ROY PLUME 02/18/2005 07/08/2005 12
Record of Decision OU 12 - ROY PLUME 09/30/2008 12
Remedial Design OU 12 - ROY PLUME 03/06/2008 03/31/2009 12
Remedial Action OU 12 - ROY PLUME 02/10/2009 09/29/2011 12
Remedial Action OU 12 - ROY PLUME 10/11/2010 09/19/2014 12
Removal OU 13 - PCB 04/05/2011 07/25/2012 13
Removal OU 13 - PCB 10/15/2007 09/30/2008 13
Combined Remedial Investigation/Feasibility Study OU 13 - PCB 03/06/2008 05/26/2010 13
Record of Decision OU 13 - PCB 04/15/2014 13
Combined Remedial Investigation/Feasibility Study OU 14 - MMRP 06/14/2011 14
Remedial Design OU 14 - MMRP 01/12/2015 14
Remedial Design OU 14 - MMRP 10/17/2014 14
Remedial Investigation OU 15 - INDOOR AIR PROGRAM 12/10/2014 05/27/2015 15
Feasibility Study OU 15 - INDOOR AIR PROGRAM 11/30/2016 15

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.