Superfund Information Systems: Site Profile

Superfund Site:

JACOBS SMELTER
STOCKTON, UT

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 12/08/1998
Proposed to the National Priorities List 07/22/1999
Finalized on the National Priorities List 02/04/2000
Remedial Investigation Started 01/20/1999
Remedy Selected 07/29/1999
Remedial Action Started 02/09/2000
Final Remedial Action Started Estimated Dec 2019 - Feb 2020
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/30/2015
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 05/03/2007 00
Removal (EPA Performed) OU 00 - SITEWIDE 03/03/1999 10/02/2000 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/30/2005 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/22/2010 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/30/2015 00
Five-Year Review OU 00 - SITEWIDE Estimated Sep - Nov 2020 00
Combined Remedial Investigation/Feasibility Study (State Performed) OU 01 - RESIDENTIAL SOILS 01/20/1999 07/29/1999 01
Proposed Plan (State Performed) OU 01 - RESIDENTIAL SOILS 05/26/1999 05/26/1999 01
Record of Decision (State Performed) OU 01 - RESIDENTIAL SOILS 07/29/1999 01
Remedial Design (State Performed) OU 01 - RESIDENTIAL SOILS 08/10/1999 12/20/1999 01
Remedial Action (State Performed) OU 01 - RESIDENTIAL SOILS 02/09/2000 03/29/2001 01
Partial NPL Deletion (EPA Performed) OU 01 - RESIDENTIAL SOILS 09/04/2001 01
Administrative Order of Consent (EPA Performed) OU 02 - NON RESIDENTIAL PORTION 07/02/2001 02
Removal (PRP Performed, EPA Oversight) OU 02 - NON RESIDENTIAL PORTION 08/15/2001 11/28/2001 02
Removal (EPA Performed) OU 02 - NON RESIDENTIAL PORTION 10/15/2010 05/31/2011 02
Remedial Investigation (State Performed) OU 02 - NON RESIDENTIAL PORTION 03/25/1999 07/23/2003 02
Feasibility Study (State Performed) OU 02 - NON RESIDENTIAL PORTION 06/18/2001 09/29/2016 02
Proposed Plan (State Performed) OU 02 - NON RESIDENTIAL PORTION 06/18/2001 09/29/2016 02
Proposed Plan (State Performed) OU 02 - NON RESIDENTIAL PORTION 07/31/2004 07/31/2004 02
Record of Decision (State Performed) OU 02 - NON RESIDENTIAL PORTION 09/29/2016 02
Remedial Design (State Performed) OU 02 - NON RESIDENTIAL PORTION 07/10/2003 Estimated Dec 2019 - Feb 2020 02
Remedial Action OU 02 - NON RESIDENTIAL PORTION Estimated Dec 2019 - Feb 2020 Estimated Sep - Nov 2021 02
Operation and Maintenance OU 02 - NON RESIDENTIAL PORTION Estimated Jun - Aug 2021 02
Administrative Order of Consent (EPA Performed) OU 03 - UNION PACIFIC 08/02/1999 03
Removal (PRP Performed, EPA Oversight) OU 03 - UNION PACIFIC 10/18/1999 02/27/2002 03
Partial NPL Deletion (EPA Performed) OU 03 - UNION PACIFIC 11/29/2005 03
Administrative Order of Consent (EPA Performed) OU 04 - KENNECOTT WATERMAN AREA PARCEL 08/28/2008 04
Removal (PRP Performed, EPA Oversight) OU 04 - KENNECOTT WATERMAN AREA PARCEL 09/15/2008 09/16/2009 04
Partial NPL Deletion OU 04 - KENNECOTT WATERMAN AREA PARCEL Estimated Dec 2020 - Feb 2021 04
Combined Remedial Investigation/Feasibility Study OU 06 - CHICAGO AND CARSON BOOZER SMELTERS OU6 Estimated Mar - May 2020 06

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.