Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed Not Yet Achieved
Proposed to the National Priorities List 02/26/2002
Finalized on the National Priorities List 10/24/2002
Remedy Selected 05/10/2010
Remedial Action Started 04/22/2010
Remedy Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 06/22/2015
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 06/01/2000 04/11/2016 00
Five-Year Review OU 00 - SITEWIDE 06/22/2015 00
Removal OU 01 - EXPORT PLANT 06/01/2000 11/22/2003 01
Removal OU 01 - EXPORT PLANT 06/05/2000 02/07/2003 01
Combined Remedial Investigation/Feasibility Study OU 01 - EXPORT PLANT 12/22/2006 05/10/2010 01
Record of Decision OU 01 - EXPORT PLANT 05/10/2010 01
Remedial Design OU 01 - EXPORT PLANT 04/22/2010 10/06/2011 01
Remedial Action OU 01 - EXPORT PLANT 04/22/2010 07/08/2013 01
Operation and Maintenance OU 01 - EXPORT PLANT 01/01/2016 01
Removal OU 02 - SCREENING PLANT 06/01/2000 06/22/2003 02
Removal OU 02 - SCREENING PLANT 07/12/2004 11/30/2004 02
Combined Remedial Investigation/Feasibility Study OU 02 - SCREENING PLANT 12/22/2006 05/10/2010 02
Record of Decision OU 02 - SCREENING PLANT 05/10/2010 02
Remedial Design OU 02 - SCREENING PLANT 04/22/2010 09/30/2010 02
Remedial Action OU 02 - SCREENING PLANT 04/22/2010 05/15/2012 02
Operation and Maintenance OU 02 - SCREENING PLANT 08/01/2013 02
Removal OU 03 - MINE 05/01/2001 06/22/2003 03
Removal OU 03 - MINE 06/08/2017 03
Removal OU 03 - MINE 07/08/2016 09/30/2016 03
Removal OU 03 - MINE 09/26/2012 10/01/2013 03
Combined Remedial Investigation/Feasibility Study OU 03 - MINE 09/17/2007 03
Removal OU 04 - REMEDIAL SITEWIDE 04/09/2008 06/15/2009 04
Combined Remedial Investigation/Feasibility Study OU 04 - REMEDIAL SITEWIDE 03/14/2002 02/08/2016 04
Record of Decision OU 04 - REMEDIAL SITEWIDE 02/08/2016 04
Remedial Design OU 04 - REMEDIAL SITEWIDE 12/14/2015 04/07/2016 04
Remedial Action OU 04 - REMEDIAL SITEWIDE 03/22/2016 04
Removal OU 05 - STIMSOM LUMBER 05/03/2005 10/05/2005 05
Combined Remedial Investigation/Feasibility Study OU 05 - STIMSOM LUMBER 12/22/2006 05
Remedial Design OU 05 - STIMSOM LUMBER 08/30/2016 05
Remedial Action OU 05 - STIMSOM LUMBER 09/29/2016 05
Removal OU 06 - BURLINGTON NORTHERN RR 08/13/2003 04/21/2010 06
Combined Remedial Investigation/Feasibility Study OU 06 - BURLINGTON NORTHERN RR 09/25/2013 02/08/2016 06
Combined Remedial Investigation/Feasibility Study OU 07 - TROY 09/01/2004 07
Combined Remedial Investigation/Feasibility Study OU 08 - STATE HIGHWAYS 03/31/2010 08
Remedial Design OU 08 - STATE HIGHWAYS 09/27/2017 08
Remedial Action OU 08 - STATE HIGHWAYS 09/27/2017 08

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.