Superfund Information Systems: Site Profile

Superfund Site:

BONITA PEAK MINING DISTRICT
UNINCORPORATED, CO

Cleanup Progress

Sign up for this Superfund site’s mailing list

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site-Wide Milestones

Milestone Date(s)
Preliminary Assessment/Site Investigation Completed 07/22/1999
Proposed to the National Priorities List 04/07/2016
Finalized on the National Priorities List 09/09/2016
Remedy Selected Not Yet Achieved
Remedial Action Started Not Yet Achieved
Construction Completed Not Yet Achieved
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review Not Yet Achieved
Site Ready for Reuse and Redevelopment Not Yet Achieved

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Removal OU 00 - SITEWIDE 01/12/2017 00
Removal OU 00 - SITEWIDE 07/16/2017 00
Combined Remedial Investigation/Feasibility Study OU 01 - OU1 SITEWIDE - REMEDIAL 05/19/2016 01
Remedial Investigation OU 02 - OU2 MAYFLOWER 05/10/2017 02

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.