Superfund Information Systems: Site Profile

Superfund Site:

FMC CORP. (YAKIMA)
YAKIMA, WA

Cleanup Progress

On this page:

Cleaning up Superfund sites is a complex, multi-phase process. Learn more:

Site Milestones

Milestone Date(s)
Initial Assessment Completed 07/28/1982
Proposed to the National Priorities List 12/30/1982
Finalized on the National Priorities List 09/08/1983
Remedial Investigation Started 07/31/1987
Final Remedy Selected 09/14/1990
Final Remedial Action Started 04/23/1992
Construction Completed 09/01/1993
Deleted from National Priorities List Not Yet Achieved
Most Recent Five-Year Review 09/05/2018
Site Ready for Reuse and Redevelopment 10/29/2012

Top of Page


Cleanup Schedule by Operable Unit

During cleanup, a site can be divided into a number of distinct areas depending on its complexity. These areas, called operable units (OUs), may address geographic areas, specific problems, or areas where a specific action is required. Examples of typical operable units include construction of a groundwater pump and treatment system or construction of a cap over a landfill.

Milestone OU Start Date Completion Date OU ID
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 07/31/1987 00
Administrative Order of Consent (EPA Performed) OU 00 - SITEWIDE 05/31/1988 00
Removal (PRP Performed, EPA Oversight) OU 00 - SITEWIDE 05/31/1988 03/16/1989 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/29/1998 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/29/2003 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/19/2008 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/18/2013 00
Five-Year Review (EPA Performed) OU 00 - SITEWIDE 09/05/2018 00
Consent Decree (EPA Performed) OU 01 - REMEDIAL 12/06/1991 01
Combined Remedial Investigation/Feasibility Study (PRP Performed, EPA Oversight) OU 01 - REMEDIAL 07/31/1987 09/14/1990 01
Proposed Plan (EPA Performed) OU 01 - REMEDIAL 08/15/2011 08/15/2011 01
Record of Decision (EPA Performed) OU 01 - REMEDIAL 09/14/1990 01
Record of Decision Amendment (EPA Performed) OU 01 - REMEDIAL 09/27/2011 01
Explanation of Significant Differences (EPA Performed) OU 01 - REMEDIAL 04/21/1993 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - REMEDIAL 08/23/1991 04/23/1992* 01
Remedial Design (PRP Performed, EPA Oversight) OU 01 - REMEDIAL 08/23/1991* 05/30/1992 01
Remedial Action (PRP Performed, EPA Oversight) OU 01 - REMEDIAL 04/23/1992 07/01/1994 01

*NOTE: This date may not reflect the actual start or actual completion of the milestone. Either the lead for this activity changed, the project was phased, or the project did not fit the normal definitions of activities tracked in this table.

NOTE: Dates and estimated dates will not display for all milestones. Estimated dates only display for milestones planned within the next three fiscal years. Estimated dates and start dates will not display for the following enforcement milestones: Administrative Order of Consent, Consent Decree and Unilateral Administrative Order. Start dates will not display for the following document milestones: Five-Year Review, Record of Decision, Record of Decision Amendment, Explanation of Significant Differences and Partial NPL Deletion.

DISCLAIMER: The data on this page are derived from the Superfund Enterprise Management System and are solely for informational purposes. The data cannot be relied upon to create any substantive or procedural rights or requirements enforceable by any party in litigation with any member of the public, states, tribes, the United States or any federal agency. EPA reserves the right to change these data at any time without public notice.