Superfund Site Profile

Protectiveness Statement
Compass Industries Superfund site (the site) fifth Five-Year Review: The remedy currently protects human health and the environment.

Current Status

The City of Sand Springs maintains the site and performs routine maintenance and sampling. The cleanup was completed in June 1991, and the site was removed from the National Priorities List on July 18, 2002. The Environmental Protection Agency and the Oklahoma Department of Environmental Quality will began activities related to the Five-Year Review (FYR) in July 2015. The previous FYR, completed in 2010, found that the selected remedy for the Site is currently performing as intended, and is considered protective of human health and the environment.

Site Background

Compass Industries Landfill is located in Tulsa County, Oklahoma. The abandoned facility, located in a former limestone quarry, was a municipal landfill between 1972 and the early 1980s. During operation, the landfill accepted about 620,000 cubic yards of solid, liquid and sludge wastes, including acids, caustics, solvents and potentially carcinogenic materials. Landfilling activities contaminated soil and groundwater with hazardous chemicals. Following cleanup, the U.S. Environmental Protection Agency (EPA) took the site off the Superfund program’s National Priorities List (NPL) in 2002.

Purpose and Process for Five-Year Review
The Five-Year Review (FYR) evaluates the implementation and performance of a remedy to determine continued protection of human health and the environment. The FYR report documents methods, findings and conclusions. In addition, it identifies any issues found during the review, and documents recommendations to address them.

The EPA prepares FYRs pursuant to the Comprehensive Environmental Response, Compensation and Liability (CERCLA) Section 121, and the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). This is the fifth FYR for the Compass Industries Superfund site.

The EPA initiated the fifth FYR for the site in June 2015. A press release announcing the commencement of the FYR was issued in June 2015. A site inspection was performed on July 10, 2015, to assess the protectiveness of the remedy and determine if any major changes occurred in and around the site that jeopardized the remedy. The EPA interviewed various entities with knowledge of the site to provide additional information concerning the site status. All the information pertaining to the site was evaluated.

The fifth FYR for the site was completed on March 25, 2016. The EPA concluded that the exposure assumptions, toxicity data, cleanup levels and remedial action objectives used at the time of the remedy selection are still valid. No additional criterion was identified to dispute the protectiveness of the remedy.

Progress Since Last Five-Year Review
The 2011 FYR included five issues and recommendations. The issues identified in the previous report are resolved, and the recommendations, where appropriate, were instituted as follows:
1. Update of the Operations and Maintenance Plan completed;
2. Surface water sampling discontinued;
3. Settlement surveys projected to be completed prior to the next FYR;
4. Continued monitoring and sampling of seeps;
5. Continued semi-annual site inspections and conduct maintenance as necessary.

Recommendations/Follow-up Actions
The FYR did not identify any issues that may affect long-term protectiveness of the current remedy. The next FYR will be completed by March 25, 2021.

National Priorities List

Proposal Date: September 8, 1983
Final Listing Date: September 21, 1984
Final Deletion Date: July 18, 2002



Yes (06/30/1992)
Human Exposure

Under Control
Contaminated Ground
Water Status
Under Control
Site-Wide Ready for
Anticipated Use?